Party walls, rights of light and permitted development rights
Contents |
[edit] Introduction
Many landlords are putting in place plans to add additional storeys to properties in town centre locations following changes to Permitted Development Rights. This replaces the need for landlords to apply for planning consent to build upwards.
However, these new planning rights do not provide complete freedom and landlords tempted by the financial rewards of increased lettable space are advised to familiarise themselves with other relevant legislation.
[edit] Party walls and PDR
Would-be developers should be aware that although planning consent may no longer be required, party wall legislation remains in place.
Any upwards extension has the potential to impact on the structure and fabric of a neighbouring property and therefore, a building owner must serve notice to affected neighbours under the Party Wall etc. Act 1996. The Act requires two months’ notice to enable the neighbouring owners (freehold and/or leasehold) to either agree or dissent to the works. At this point an appointed party wall surveyor must undertake a schedule of condition of the neighbouring properties to provide effective dispute resolution.
Importantly, landlords should clarify the technical aspects of an extension. For example, if the building works result in alterations to a leaseholder’s ceiling (such as to embed a steel structure) their rights will be affected. If the extension is built onto a parapet, party wall rights may not be an issue but other issues – such as rights to light, the impact on services and any disruption caused during construction – may require consideration.
Many residents of top floor flats assume that they have rights over roofs. But while they may have access, they do not necessarily have protected rights. Skylights may be similarly affected.
For more information see: Party Wall Act.
[edit] Rights of light and PDR
In the absence of a planning process to scrutinise projects that will add to building heights, the issue of rights of light becomes a very serious consideration, and one with significant consequences.
Because daylight and sunlight assessments are a component of a planning application, they are currently required at an early stage in the process. The planning system also necessitates that local residents are consulted on a planning application, allowing those with legitimate concerns to assert their point of view. With this step removed, developers could potentially proceed unaware of any objections – resulting in building works then being halted through an injunction either during the process or post-completion.
For more information see: Rights to light.
So while developers might look set to gain from the opportunity to create additional storeys, in reality the situation is precarious. Without the stringent procedures and ultimately the reassurance that the planning system offers, developers could potentially embark on building works and only on completion suffer significant consequences.
There are many examples of developers of extensions being ordered to reverse changes, not because of planning issues, but because of the sometimes more opaque requirement of party wall and rights of light legislation.
An inevitable consequence of the extension of Permitted Development Rights will be an increase in the number of both investigations and claims. Developers are advised to seek professional advice at an early stage to avoid the significant expense of having to pull down an extension and begin again.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.