On-site generation of heat and power
Contents |
[edit] The challenge
The distributed power delivery model is outdated, wasteful and unreliable.
Providing sustainable energy is vital for the on-going health and viability of cities in the future. Dependence on the distributed power delivery model in major cities such as New York City is irresponsible and untenable.
One critical flaw of distributed power systems is their vulnerability to weather events. Climate Central’s analysis of 28 years of power outage data, supplied to the Federal Government and the North American Electric Reliability Corporation by utilities, shows that since 2003 (after stricter reporting requirements were widely implemented), the average annual number of weather-related power outages has doubled.
Non-weather related outages have also increased in that time, but weather caused 80% of all outages between 2003 and 2012.
They are also extremely wasteful. Nearly two-thirds of the fuel used to generate power in a power plant never reaches its destination as electricity. Most of that is discarded at the power plant as heat. Additional losses are due to inefficiencies in transmittance, mainly due to resistance of the utility power line.
A better, cleaner and more effective way to heat and power buildings, campuses and cities exists. It is time to move away from the outdated model of distributed energy to something more sophisticated, calibrated and sustainable.
[edit] The idea
Localised, point generation of heat and power – onsite generation – provides an independent, responsive, sustainable method of energy supply.
On-site generation can include renewable energy technologies, such as photovoltaics, anaerobic digestion, distributed steam for heating and power and co-generation technologies. Over the past five years, interest has been growing in distributed generation systems, co-generation/Combined Heat and Power (CHP) plants as well as microgrids.
With on-site generation, reliance on distributed systems is reduced or even abolished, helping to avoid distribution losses and allowing independence from grid-related outages, shortages or demands. The availability of critical infrastructure in the event of natural or man-made disasters is in no small way driving this current interest in on-site generation methodologies.
A number of market drivers explain this growing interest in on-site generation, including low natural gas costs, increasing electricity costs and a desire to maintain manufacturing equipment uptime. More stringent environmental regulations have increased utility costs (and central plants) as well.
Likewise, environmental drivers around clean power, clean air and pollutant control have created an environment for a cleaner, more efficient method of generating and delivering power.
CHP simultaneously generates power and thermal energy by recycling the captured heat from electricity production and transforming it into useful thermal energy. As a result, CHP technology converts up to 85% of fuel into useful energy and consumes 40% less fossil fuel than traditional technologies. By delivering a localised, uninterrupted and efficient energy supply, CHP reduces fuel requirements, mitigates greenhouse gas emissions, saves money and reduces exposure to market fluctuations as well as severe weather.
According to a report by management consultants ICF International, CHP represents 7% of current US generating capacity. 70% of CHP capacity is in use for industrial purposes. Of the total US CHP generating capacity, 87% is natural gas-fired.
[edit] The impact
On-site generation reduces greenhouse gas emissions and supports critical services in the event of a natural disaster.
According to the American Council for an Energy-Efficient Economy, CHP will conservatively contribute approximately 46 million metric tons in CO2 emissions savings nationwide by the year 2030. While these savings are specific to CHP, the potential reduction of greenhouse gases for all forms of on-site generation is tremendous.
Likewise, the benefits of a reliable means of providing power to critical systems cannot be overstated. In New York City, after experiencing the impact of Hurricane Sandy, the resilience and reliability of power supply has become paramount.
During the storm, while the majority of Manhattan was without power, most of New York University’s (NYU) Greenwich Village campus had electricity, heat and hot water. The traditional utility grid struggled to maintain delivery of power and the majority of lower Manhattan was without electricity. However, NYU was able to generate its own electricity and heat via a 15 MW peak co-generation plant.
[edit] Barriers to innovation – and solutions
Financial cost is a major hurdle to widespread use of on-site generation.
Many university campuses, industrial facilities and hospitals in North America have adopted a localised co-generation approach to meeting heating and power demands. The challenge lies in translating this model to other environments. A major hurdle is the cost – upfront and long term – of on-site generation.
In New York, standby tariffs are imposed when operating in conjunction with the grid. Utilities charge for additional infrastructure that is used when on-site generation fails or is down for maintenance. This added operational cost hurts ROI, de-incentivising on-site generation methods from being considered. A less onerous tariff would improve financial metrics.
Utility requirements for interconnection to the grid are also costly and expensive. Such requirements include transfer trip systems, protective relaying, fault current mitigation, metering, communications systems and isolation transformers. The approval process for this interconnection is equally burdensome and lengthy. A streamlined process for interconnection must be developed.
Utility gas mains must be reinforced if a natural gas-driven co-generation strategy is to be adopted and this too, creates additional costs by the entity installing and operating the onsite generation system.
Finally, although on-site generation technologies are incentivised, the steep upfront costs and the long-term operational expenses present a financial burden that far outweighs the incentives. Currently, incentive programmes exist only for grid-connected systems when installed in New York City.
New York State Energy Research and Development Authority (NYSERDA) will review off-grid systems for potential incentives, but only on a case-by-case basis. For widespread uptake of on-site generation technologies, in addition to incentives provided for grid connected systems, incentives for systems operating only in island mode must also be made readily available.
[edit] The way forward
On-site generation must make sense from a business standpoint.
- Utilities, developers, technology providers, energy consumers, environmental agencies and government must all work together to provide a complete solution that fits the business case.
- Utilities must pay their fair share of costs that are offset by a developer that adds megawatts (MWs) of power to the grid.
- Technology providers must sell new technology at a fair price.
- Energy consumers must support the effort through conservation of energy, but they also must be willing to pay an additional expense for clean reliable power.
- Environmental agencies must set realistic expectations and not impose the excessive, unattainable.
- Government must lead the change by requiring further incentives (for upfront costs as well as long-term operations) and oversight to ensure transparency among all involved parties.
Written by:
- Sydney Mainster, Sustainability Manager, Royal Realty Corp, The Durst Organization, USA.
- Philip Skalaski, Vice-President, Engineering and Energy Services, The Durst Organization, USA.
- Karole Colangelo, Vice President, Communications, Veolia, USA.
This article was originally published on the Future of Construction Knowledge Sharing Platform and the WEF Agenda Blog.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.