NEC early warning notices - a tool of mutual benefit
Rudi Klein, NEC Users’ Group President and Chief Executive at Specialist Engineering Contractors' (SEC) Group argues that the sooner we can appreciate that early warning notices are a tool of mutual benefit to both parties – and not designed to advantage one side over the other – the better.
Contents |
[edit] Introduction
I receive regular feedback from construction firms regarding the operation of NEC early warning notices. They normally comprise one or more of the following comments:
- "I always issue early warning notices, whatever the problem, to ensure I get a compensation event."
- "The other side issues early warning notices to establish it is my fault and I have to fix it immediately."
- "I am wary of issuing early warning notices because the other side uses them against me in the event of a dispute."
- "Everyone on the project ignores early warning notices."
It is clear that there are still some misconceptions about NEC early warning notices.
[edit] Risk management tool
Early warning notices have been a feature of NEC from the start – their inclusion separated NEC from the rest of the contractual pack.
They were introduced as a risk management tool because it is common sense that dealing with risk – wherever it comes from – as soon as it becomes apparent is far cheaper than trying to manage the risk and/or its consequences much later on.
Clause 16 of most NEC contracts makes clear the circumstances in which either party would be expected to issue an early warning notice.
An early warning notice must be issued as soon as a party becomes aware of 'any matter' which could affect the total of the prices, could delay completion or a key date, or impair the performance of the works in use.
Also, the contractor may give an early warning notice relating to any matter which could increase its total cost. Early warning matters should be entered on the risk register.
[edit] Mutual benefit to parties
Early warning notices should not be issued for the purpose of allocating responsibility or liability. A party attempting to do this could be failing to act in the NEC clause 10, 'spirit of mutual trust and co-operation'. When dealing with matters which are the subject of an early warning notice, the emphasis should be on agreeing the steps required to address the matter rather than allocating blame.
Certainly ignoring early warning notices is a dangerous game. Apart from a possible breach of clause 10, any compensation event that may follow is likely to be costlier to the client than if the matter had been dealt with at the outset.
But remember there is no direct link between early warning notices and compensation events. An early warning notice might not lead to a compensation event and a compensation event might occur without an early warning notice.
Some of the confusion around early warning notices can be accounted for by people having grown up within an adversarial contracting culture. Such culture should be discarded when using NEC.
This article was written by Rudi Klein, NEC Users’ Group President and Chief Executive at Specialist Engineering Contractors' (SEC) Group.
It was originally published here on 17 July 2017 by ICE.
--The Institution of Civil Engineers
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.