Management contracting - pros and cons
Management contracting is a procurement route in which the works are constructed by a number of different works contractors who are contracted to a management contractor. The management contractor is generally appointed by the client early in the design process so that their experience can be used to improve the cost and buildability of proposals as they develop, as well as to advise on packaging and the risks of interfaces.
The agreement between client and management contractor is likely to cover both pre-construction and construction activities, with a notice to proceed between the two, before which works contracts cannot be let.
For more information see: Management contracting.
Management contracting can be beneficial on complex and/or specialist projects made up of a number of packages individually appointed to the best-suited subcontractor. This means that there is the potential for the highest-quality of delivery.
It can also be beneficial for the client in that they are able to retain control of the design while drawing on the experience and expertise of a construction specialist as part of the professional team, since the management contractor contributes to the design process. At the same time, the client is able to move risks or procurement and delivery onto the management contractor who is responsible both for project management and carrying out the works.
In addition, rather than the contractor tendering a fixed price, they can provide cost savings for the client, as well as time savings by tendering some of the work packages early (such as groundworks) and overlapping the design and construction activities. This allows for a quick start on site.
There can be also be considerable flexibility in the design, with changes being made throughout the construction process (albeit with potential cost implications).
However, it can be unsuitable as a procurement route for inexperienced clients since, although they can have more control over the design, works usually begin before the nature of the completed building is known. The lack of available specialists may also cause unproductive gaps in the work to be undertaken.
There is a body of opinion that believes that if a management contractor operating on a cost plus fee arrangement pursues a works contractor in court for non-performance, the management contractor is unable to prove loss and damages. This is because the loss is simply passed on to the client, and so it is the client that has incurred the damage. This has increased the tendency for clients to require direct warranties from each works contractor.
A decision needs to be made as to whether the client wishes to retain the services of both an independent cost consultant or to transfer cost planning, reporting and cost control as a service to be provided by the management contractor. A judgement has to be made on the competence and experience of the management contractor's proposed quantity surveying and cost estimating team and whether the client has a competent individual to police the financial aspects of the management contractor’s consultancy agreement.
[edit] Related articles on Designing Buildings
- Construction contract.
- Construction management contract.
- Design and build - pros and cons.
- Design build operate (DBO).
- Design liability.
- Employer’s requirements.
- Management Building Contract.
- Management contract: outline work plan.
- Management contractor.
- Traditional contract - pros and cons.
- Works contractor.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.
Comments