Input specification vs output specification
Traditional specifications are ‘input specifications’. They are prescriptive, that is, they describe in detail the products, materials and work (the inputs) required by a contract. Typically, the development of the solution required by the contract is complete and no (or little) further development is required by the supplier. The specification is considered to be a ‘closed specification’.
Prescriptive input specifications give the client certainty about the end product when making investment decisions, but place a greater burden on them to ensure the product has been thoroughly considered, developed and described. They tend to be used where a very specific end result required.
Output specifications define only the outcomes (or outputs) that are required by the contract, that is, what it will enable the client to do. They are open specifications that do not attempt to address how those outputs might be achieved. For example, an output specification might require the provision of a space for teaching 30 primary pupils, but it would not specify the nature of the space, the types of doors and windows etc. The standard for what is required might be defined, for example, by reference to performance targets.
It is argued that output specifications can get the best value from the supply team by allowing them to adopt innovative solutions to the client's requirements and reduce whole-life costs rather than simply developing the client's pre-conceived solutions at the lowest price.
For more information see: Output-based specification.
[edit] Related articles on Designing Buildings Wiki
- Briefing documents.
- Feasibility studies.
- Final specifications.
- Insulation specification.
- Outline specification.
- Output specification
- Output-based specification.
- Performance specification.
- Prescriptive specification.
- Procurement.
- Service level specification.
- Specification.
- Tender documentation.
- Tender process.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
How orchards can influence planning and development.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.