Input specification vs output specification
Traditional specifications are ‘input specifications’. They are prescriptive, that is, they describe in detail the products, materials and work (the inputs) required by a contract. Typically, the development of the solution required by the contract is complete and no (or little) further development is required by the supplier. The specification is considered to be a ‘closed specification’.
Prescriptive input specifications give the client certainty about the end product when making investment decisions, but place a greater burden on them to ensure the product has been thoroughly considered, developed and described. They tend to be used where a very specific end result required.
Output specifications define only the outcomes (or outputs) that are required by the contract, that is, what it will enable the client to do. They are open specifications that do not attempt to address how those outputs might be achieved. For example, an output specification might require the provision of a space for teaching 30 primary pupils, but it would not specify the nature of the space, the types of doors and windows etc. The standard for what is required might be defined, for example, by reference to performance targets.
It is argued that output specifications can get the best value from the supply team by allowing them to adopt innovative solutions to the client's requirements and reduce whole-life costs rather than simply developing the client's pre-conceived solutions at the lowest price.
For more information see: Output-based specification.
[edit] Related articles on Designing Buildings Wiki
- Briefing documents.
- Feasibility studies.
- Final specifications.
- Insulation specification.
- Outline specification.
- Output specification
- Output-based specification.
- Performance specification.
- Prescriptive specification.
- Procurement.
- Service level specification.
- Specification.
- Tender documentation.
- Tender process.
Featured articles and news
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
Introducing a circular ecomony deposit return scheme
The government makes steps towards DRS scheme for plastic bottles and cans in England and Northern Ireland.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building 2024 judges choice winner
Once Upon a Pass by Liam Man.
CIOB Art of Building 2024 public choice winner
Fresco School by Roman Robroek.
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
How orchards can influence planning and development.