Notifiable project F10 form
The Construction (Design and Management) Regulations 2015 (CDM regulations) require that the Health and Safety Executive (HSE) must be notified of any project defined as construction under the regulations where the construction work is likely to last longer than 30 working days and have more than 20 workers working simultaneously at any point in the project, or exceed 500 person days. This can be done using an F10 form.
Regulation 6 of the CDM regulations requires that the client must give notice in writing to the HSE as soon as is practicable before the construction phase begins, or arrange for someone else to do this on their behalf.
The notice must include the details included in schedule 1 of the regulations:
- The date of forwarding the notice.
- The address of the construction site or precise description of its location.
- The name of the local authority where the construction site is located.
- A brief description of the project and the construction work that it entails.
- The following contact details of the client: name, address, telephone number and (if available) an email address.
- The following contact details of the principal designer: name, address, telephone number and (if available) an email address.
- The following contact details of the principal contractor: name, address, telephone number and (if available) an email address.
- The date planned for the start of the construction phase.
- The time allocated by the client under regulation 4(1) for the construction work.
- The planned duration of the construction phase.
- The estimated maximum number of people at work on the construction site.
- The planned number of contractors on the construction site.
- The name and address of any contractor already appointed.
- The name and address of any designer already appointed.
- A declaration signed by or on behalf of the client that the client is aware of the client duties under these Regulations.
Where details are not available (such as the details of the principal contractor) they must be provided when they are available, and in any event, before construction works begin.
The notice must also be clearly displayed in the construction site office in a comprehensible form where it can be read by any worker engaged in the construction work; and if necessary, be periodically updated.
HSE will take 10 days to process notifications by manual form. (Ref. HSE, F10 Manual input form frequently asked questions.) However, notification can now be carried out online by filling out an e-form and manual notification forms will cease to be available after 31 March 2015. Confirmation of receipt of an e-F10 form should be received shortly after submission.
[edit] Related articles on Designing Buildings
- Accident book.
- Accident report.
- CDM.
- CDM for self-builders and domestic clients.
- Competent person.
- Fee for intervention.
- First aider.
- Health and safety.
- Health and Safety Executive.
- Health and safety inspector.
- Incident reporting system.
- Inspections focus on occupational lung disease.
- Licence for Alterations for Apartment.
- Principal contractor.
- Reporting accidents and injuries on construction sites.
- Site records and registers.
- What approvals are needed before construction begins.
[edit] External references.
- HSE How to notify a project.
- Schedule 1 of the CDM regulations.
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
Comments