Dayworks in construction
Daywork is a means by which a contractor is paid for specifically instructed work on the basis of the cost of labour, materials and plant plus a mark up for overheads and profit. It is generally used when work cannot be priced in the normal way.
NRM2, RICS new rules of measurement, Detailed measurement for building work defines daywork as; '... the method of valuing work on the basis of time spent by the contractor’s workpeople, the materials used and the plant employed.'
Examples of when daywork may be applied are when unforeseen obstructions are encountered during ground works or when work is instructed for which there are no comparative rates in a bill of quantities.
It is usual for most contracts to contain clauses that provide a method of evaluating variations, additional work and instructions by using existing contract rates and prices. NEC contracts favour pre-agreed sums based on acceptance of a contractor’s quotation.
There are two basic options as to how daywork rates can be priced:
Option A – a percentage addition
- Prime cost to which a percentage is added for overheads, profit and incidental costs.
Option B – all inclusive rates
- All inclusive rates are quoted at tender and incorporated in the contract documents. These include an allowance for overheads and profit, either fixed for the period of the contract, or, in the case of contract conditions that are index linked, subject to an inflation allowance.
[edit] Related articles on Designing Buildings
Featured articles and news
ECA digital series unveils road to net-zero.
Retrofit and Decarbonisation framework N9 launched
Aligned with LHCPG social value strategy and the Gold Standard.
Competence framework for sustainability
In the built environment launched by CIC and the Edge.
Institute of Roofing members welcomed into CIOB
IoR members transition to CIOB membership based on individual expertise and qualifications.
Join the Building Safety Linkedin group to stay up-to-date and join the debate.
Government responds to the final Grenfell Inquiry report
A with a brief summary with reactions to their response.
A brief description and background to this new February law.
Everything you need to know about building conservation and the historic environment.
NFCC publishes Industry White Paper on Remediation
Calling for a coordinated approach and cross-departmental Construction Skills Strategy to manage workforce development.
'who blames whom and for what, and there are three reasons for doing that: legal , cultural and moral"
How the Home Energy Model will be different from SAP
Comparing different building energy models.
Mapping approaches for standardisation.
UK Construction contract spending up at the start of 2025
New construction orders increase by 69 percent on December.
Preparing for the future: how specifiers can lead the way
As the construction industry prepares for the updated home and building efficiency standards.
Embodied Carbon in the Built Environment
A practical guide for built environment professionals.
Updating the minimum energy efficiency standards
Background and key points to the current consultation.
Heritage building skills and live-site training.
Comments
There is a great mobile phone App that lets you quickly create a daywork or just a resource estimate and send it to the office in minutes, the App date stamps start and finish photos to help you prove the record is a true reflection of the works. It also allows you to quickly get pre-authorisation of the daywork prior to starting the works. Here's the link http://www.constructionrates.co.uk/Rate_Gen/Android_Mobile_Tablet_Smart_Phone_Daywork_App_UK_Construction_Industry.htm