Contract amendment
A contract amendment is to a formal change or modification to the terms and conditions of an existing construction contract. This can be necessary to accommodate adjustments that may arise during the course of a project, for example:
- Changes in the scope of work to be performed, including additions, deletions, or modifications to the original project plans and specifications.
- Adjustments to the project timeline, which might include extending or shortening the completion date or adjusting intermediate milestones.
- Modifications to the contract price, which could involve increasing or decreasing the overall budget based on the changes to the scope of work or other factors. It can also include changes to the payment schedule.
- Substitutions or changes in materials, products, or workmanship specifications that were initially agreed upon.
- Adjustments to ensure the contract remains compliant with any new or updated laws, regulations, or standards that may come into effect during the project.
- Revisions to the allocation of risks and responsibilities between the parties involved, such as changes in insurance requirements or liability clauses.
- Changes to the methods and processes for resolving disputes, which could involve amending arbitration clauses, mediation procedures, or other conflict resolution mechanisms.
Contract amendments are typically documented through formal written agreements signed by all parties involved in the original contract. This documentation ensures that there is a clear, mutual understanding of the changes and helps prevent disputes related to misunderstandings or misinterpretations of the modifications.
See also: Variations.
[edit] Related articles on Designing Buildings
- Abortive work in building design and construction.
- Architect's instruction.
- Change control procedure for building design and construction.
- Change order for construction contracts.
- Compensation event.
- Confirmation of verbal instruction.
- Contract sum.
- Extension of time EOT in construction contracts.
- How to prepare a claim for an extension of time.
- Loss and expense.
- Payment for extra work.
- Prime cost sum.
- Provisional sum.
- Relevant event.
- Relevant matter.
- Scope of work.
- Valuation of interim payments.
- Variations.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.