Construction management: tender trade contracts
The tender stage is the process of selecting and appointing trade contractors. Tendering involves a number of trade contracts, contracted by the client but managed by the construction manager. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project.
Contents |
[edit] Starting the work stage.
The construction manager and client prepare selection criteria for trade contractors and if appropriate pre-qualification questionnaires. If it is necessary and has not already been done, OJEU or other adverts are prepared.
The construction manager and client consider lists of approved trade contractors, the preferred form of contract, contract conditions and the allocation of risk. They then co-ordinate a stage start-up meeting with the consultant team, and the client to agree the programme and procedures that will be adopted for tendering. The construction manager gives any instructions necessary relating to lists of approved trade contractors, any required advertising, the form of contract, contract conditions and other requirements.
[edit] Preparing the tender documentation.
NB Throughout this stage, The lead designer co-ordinates completion of statutory approvals and other approvals and negotiations.
The construction manager obtains from the consultant team information required for the preparation of the tender documentation, pre-tender estimate and cash flow projection for the trade contracts and co-ordinates the preparation of pre-construction Information.
The construction manager co-ordinates a review of the tender documents and issues instructions to make amendments if necessary. They should produce a risk allocation report which sets out whether risks in the contract documents are retained by the client, transferred to contractors, are shared or are insured.
The client considers the tender documents (including assessment of the pre-tender estimate in relation to the budget) and risk allocation report and issues instructions to make amendments if necessary.
The construction manager instigates change control procedures for the tender documents and arranges printing of the tender documents.
[edit] Identifying potential tenderers.
The construction manager and client prepare a long list of suitable trade contractors and issue pre-qualification questionnaires. The construction manager receives completed pre-qualification questionnaires and carries out financial checks on potential tenderers (ideally the contract should not be more than 20% of the annual turnover of the potential tenderers).
The construction manager co-ordinates advice on prospective tenderers and prepares a short list of tenderers to present for client comment or approval. The client accepts or alters the initial short list of tenderers and where appropriate the construction manager arranges pre-tender interviews with the initial short list of tenderers.
The construction manager co-ordinates any amendments to the initial short list of tenderers and agrees the final short list of tenderers with the client. If necessary, following comments received during the pre-tender interviews, the construction manager instructs amendments to the tender documentation.
[edit] Identifying the preferred tenderer(s).
The construction manager collates tender documents for each of the trade contracts and arranges dispatch to and return from the tenderers.
The construction manager compiles queries from tenderers and co-ordinates responses which should be issued to all tenderers. If necessary, the construction manager arranges mid-tender interviews and/or site visits for the tenderers. If queries from the tenderers or discussions during the mid-tender interviews result in significant clarification of, or changes to, the tender documentation, the construction manager may recommend to the client that the tender period is extended.
The client receives the tenders. They may follow a formal procedure for opening and recording tenders. The construction manager co-ordinates assessment of the tenders. This may include further interviews.
The client receives the tender appraisals from the construction manager, and instructs the construction manager to enter into negotiations with the preferred tenderer(s). A reserve tenderer may be retained in the event that negotiations with the preferred tenderer are unsuccessful.
[edit] Entering into negotiations with the preferred tenderer(s).
The construction manager co-ordinates negotiations with the preferred tenderer(s). It is paramount in any negotiation that the individuals at the negotiating table either have authority to fully negotiate terms or make it clear from the start the limits of their authority. This may mean re-convening with the right people empowered to make decisions.
The construction manager co-ordinates the preparation of a tender report. The client considers the tender report and instructs the construction manager if any changes are required to the tender documents. If instructed the construction manager co-ordinates adjustments to tender documents and requests a revised tender from the preferred tenderer(s).
[edit] Appointing the trade contractor.
The construction manager collates the contract documents and arranges for the printing (engrossment) and execution of two copies, one for the client and one for the trade contractor. This can take place at a specially convened signing meeting. Alternatively, the client might retain one executed contract, with certified copies being issued to the trade contractor, this can avoid potential errors in preparing two contracts for execution. The trade contractor may be required to provide: a performance bond, warranties, evidence of insurance cover and so on.
The construction manager arranges for copies of the contract documentation (or relevant parts) to be issued to the consultant team.
The construction manager informs other tenderers that they have been unsuccessful.
NB. Trade contracts may not all be tendered at the same stage, and so this process might be repeated a number of times during the project.
Featured articles and news
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.