Construction contract engrossment
Contract engrossment is the process of preparing the final agreed form of a contract and its schedules and appendices so that it can be executed (signed). Historically, this may have involved hand-writing the contract on thick paper and having it bound. Today it is more likely to be printed and then bound.
Engrossment can be required for a wide range of legal agreements, such as; construction contracts, appointment agreements, conveyancing agreements, and so on.
Engrossed contracts are then either executed under seal (signed by the parties, witnessed and most importantly made clear that they are executed as a deed) or under hand (a 'simple contract' that is just signed by the parties). See Contracts under seal v under hand for more information.
Generally, two engrossed contracts will be prepared for execution, one for the client and one for the supplier. Alternatively, the client might retain one executed contract, with certified copies being issued to the supplier, this can avoid potential errors in preparing two contracts for execution.
NB The term engrossment can also be used in relation to the enactment of statutes, describing the process of printing the final form of an agreed Act ready for its enrolment (registration on the Parliament Roll).
[edit] Related articles on Designing Buildings
- Commercial close.
- Conformed contract.
- Contract award.
- Contracts under seal v under hand.
- Construction contract.
- Construing a contract.
- Contract conditions.
- Contract documents.
- Contract execution.
- ESignatures.
- Essentials of a contract.
- Financial close.
- Form of tender.
- Glossary of property law terms.
- Privity of contract.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.