Construction management: occupation and defects liability period
The occupation and defects liability period takes place after the client has taken possession of the development for occupation. During this stage, any defects are rectified and the final certificate is issued signifying that the construction works have been fully completed. As the development is now occupied, and the construction manager no longer has possession of the site, close co-operation is required between the construction manager and the client so as so not to disturb occupants, whose activities will take priority over trade contractors rectifying defects.
[edit] Starting the work stage.
The construction manager arranges a start-up meeting to plan the work stage.
On construction management contracts, a separate certificate of practical completion is issued for each trade contract. This means that defects liability periods may be at different times for each trade contract and as a consequence, the construction manager may continue to hold construction progress meetings and issue construction progress reports for continuing trade contracts and may have to protect completed work from continuing work.
[edit] Rectifying defects.
If the contract allows, the construction manager may review all relevant events that might be considered to have affected the completion date for each trade contract and may adjust their completion dates accordingly.
The client reports any defects in the works to the construction manager. On large projects the construction manager may set up a hot desk for responding to any complaints or to provide assistance required by the incoming occupants. The construction manager takes advice on the action necessary to rectify the defects from the consultant team, and the construction manager and client agree a programme for rectifying defects in a way that minimises disruption to the client.
If rectification works are significant, it may be necessary for the client to re-appoint the principal designer (whose appointment may have terminated on certification of project completion) and it may be necessary to amend the health and safety file.
At the end of the defects liability period for each trade contract, the construction manager arranges inspections of the works and prepares a schedule of defects which is issued to the trade contractor. The construction manager agrees the programme for rectification of items on the schedule of defects with the client and trade contractors, which should in any event be rectified within a reasonable time.
The trade contractor rectifies items listed on the schedules of defects, informs the construction manager and provides the construction manager with information for the preparation of the final account. The trade contractor and construction manager agree the final account for the trade contract.
The construction manager arranges final inspections of the trade contractors works and if satisfied issues a final statement (payment notice) for that trade contract. If the client intends to pay a different amount from that shown on the statement, then construction manager must issue a pay less notice giving the basis for the calculation of the amount they intend to pay. The client makes payment by the final date for payment. This may include the release of any remaining retention if applicable.
The construction manager completes the building owner's manual.
If a site waste management plan has been prepared, the construction manager may reconcile the planned handling of waste against what actually happened and provide an explanation of any differences.
[edit] Issuing the final certificate.
Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the project.
Issuing the final certificate will normally signify the end of the construction manager's and consultant team's appointments. If post-occupancy evaluation services are required, these may involve a new appointment.
Featured articles and news
BSRIA Statutory Compliance Inspection Checklist
BG80/2025 now significantly updated to include requirements related to important changes in legislation.
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.