CLC publishes guidance on COVID-19 impact for NEC4
In July 2021, guidance on how clients and construction firms can collaborate to avoid disputes related to the COVID-19 pandemic under NEC4 contracts was published. The Construction Leadership Council (CLC) in collaboration with NEC published joint guidance on dealing with - and accommodating - the impact of COVID-19 on work under NEC4 contracts.
The guidance adds to the suite of outputs from the CLC's Business Models: Contractual Best Practice group which has routinely called for strategic collaboration between clients and the supply chain to avoid systemic market failures and compromised project delivery.
The guidance focuses on the NEC4 Engineering and Construction Contract (ECC), although it can also be applied to the NEC4 Engineering and Construction Subcontract (ECS), NEC3 ECC and ECS, subject to some amends which are outlined within the guidance.
To help clients and the supply chain to collaborate, the joint guidance offers support in navigating a number of circumstances within the context of the COVID-19 pandemic, including:
- Act of prevention.
- Project manager's instructions.
- Compensation events.
- Evaluation of a COVID-19 related compensation event.
- Working areas.
- Resource utilisation.
- Dealing with risk on future contracts.
Steve Bratt, Chair of the CLC's Business Models Workstream, said, "Following previous guidance, CLC remained open to industry feedback, and this guidance was developed in response to a series of questions which were raised with regard to projects impacted by COVID-19 operating under NEC contracts.
"As industry continues to manage the challenges of COVID-19, we are becoming increasingly concerned that many outstanding disputes remain unresolved and much uncertainty exists with regard to future contracts. We are therefore keen to do all we can to ensure clients work with their supply chains to fairly and collaboratively manage the commercial risks caused by COVID-19. Safety is paramount, but collaborative risk sharing will ensure secure project delivery and a long-term sustainable industry.
"COVID-19, safe working procedures and wider disruption has presented all parties with unquantifiable and unmanageable risks and costs. Traditional behaviours, such as inappropriate risk transfer, will not only lead to a negative outcome on individual contracts but will almost certainly lead to systemic failure in a fragile market seeking to build back greener and better."
Peter Higgins, Chairman of the NEC4 Contract Board, said, "NEC is pleased to have worked with the Construction Leadership Council in preparing this advice on dealing with COVID related issues under NEC contracts. NEC has always been a contract focusing on the parties working together to achieve a successful contract, and this guidance will help in managing collaboratively the risks which have arisen from COVID-19."
This article originally appeared on the CIAT website. It was published on 27 July 2021.
--CIAT
[edit] Related articles on Designing Buildings Wiki
- Alternative dispute resolution for construction ADR.
- CIAT articles.
- CLC urges inclusion of fluctuations provisions in contracts.
- Construction Leadership Council CLC.
- Extension of time EOT in construction contracts.
- NEC3.
- NEC4.
[edit] External resources
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.