Advanced network planning
Programmes describe the sequence in which tasks must be carried out so that a project (or part of a project) can be completed on time.
Programmes will often identify:
- Dates and durations allocated to tasks.
- A critical path (the sequence of critical tasks upon which the overall duration of the programme is dependent).
- Tasks which can only be carried out after other tasks have been completed.
- Tasks which can be carried out simultaneously.
- 'Float' within tasks that are not on the critical path (that is, delays that can be incurred without affecting the critical path).
- The need for specific resources such as plant, services or materials and their lead time.
Developing a programme for a project can be very complex, as there are a great number of interrelated activities to consider, a change in any one of which may impact on all the others.
Advanced network planning is a process that can be used for planning, scheduling and controlling projects (or programmes – that is portfolios of projects) that consist of a large number of interrelated activities.
Network planning techniques first developed in the 1950s and included techniques such as:
- The Critical Path Method (CPM).
- The Program Evaluation and Review Technique (PERT).
- The Precedence Diagramming Method (PDM).
- The Graphical Evaluation and Review Technique (GERT).
- Systematic Network Planning (SNP).
Very broadly, these describe projects as a network of tasks, the interrelationships between which can be used to establish the most appropriate moment for their execution in order to complete the overall project on time.
Creating a network includes a number of steps:
- All the project activities are identified and defined.
- The technological sequence between activities is defined.
- A network is constructed which shows the relative priority of those relationships.
- The execution periods for each activity are estimated.
- The critical path is calculated.
- As time goes on and more information is acquired, the network is revised and re-evaluated.
A typical network will include a set of “arrow diagrams” which go from the origin node to the destination node. In this sense, the path is defined as a sequence of connected activities, which flow from the start of the project (node 1) to the end. The time required to follow one of these paths is the sum of the times corresponding to each of the activities. The critical path is that which requires the longest time to progress from inception to completion, and indicates the minimum timeframe required to complete the whole project.
Complex models can be developed that include additional information such as cost information, and may represent:
- Variables: Aspects in the model that can be changed, such as product type.
- Sensitivities: How much performance changes in response to variable changes.
- Scenarios: The range of possible changes to the network.
Advanced network planning can also be used in applications, such as health and safety management, IT asset sourcing, resource allocation, operations and maintenance scheduling and so on.
This is a complex specialist process that is simplified by the use of software that carries out analysis automatically and outputs results in ways that are easier for the project team to digest, such as gantt charts.
On large projects, the client may appoint a programme consultant who specialises in this subject, and suppliers may have their own programmers.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
A dynamic brand built for impact stitched into BSRIA’s building fabric.