Why the lowest price isn't sustainable
Contents |
[edit] Introduction
The Institute of Chartered Accountants in England and Wales (ICAEW) warned in its Audit Insight report into construction earlier this year that the ‘race to the bottom’ in construction contracting could lead to more major firms collapsing. It will also damage their supply chains, forcing more smaller firms out of business.
In preparing its report, ICAEW collaborated with auditors with many years' experience of independently examining and auditing construction firms. These included KPMG, PwC, EY, Deloitte and The Orange Partnership.
The construction sector is a key driver of growth for the UK economy, but it is a fragile one with low margins and high risks.
When construction companies and clients get it right − through project selection based on their ability to deliver, responsible tendering, diligent monitoring, and a proactive attitude to deal with issues such as cost and timetable overruns – they create contracts that are more profitable and provide more enduring value.
The report examines four key areas that need to be addressed by construction firms if they are to run sound, well-managed businesses.
[edit] Bidding for lasting value
If construction businesses want to generate sustainable profits, they need to get the price right at the tendering stage.
Some companies have become better at pricing their services realistically to reflect their true cost. But we are also seeing businesses bidding at too low a price for large complex contracts in the expectation that they will improve their profit margins because some aspect of the project will change. This is a risky strategy as unforeseen changes can quickly turn small profits into losses, and make it difficult to return to profitability.
[edit] Delivering for success
In construction, it is especially important that financial rigour is applied to key estimates and judgements throughout a project’s lifecycle. Competition is so fierce and margins so thin that reliable financial information and analysis can determine a project’s success. One way to achieve this objective is to form strong delivery teams where project managers work closely with finance and commercial teams. We do not see enough evidence of this in practice and urge firms to remedy any lack of collaboration.
[edit] Increasing transparency
The UK construction sector continues to suffer from a reputation that it lacks enough transparency, particularly on cost and performance. In many cases, poor or unexpected results are caused by a lack of internal transparency.
Executive management and boards need to ensure the tone from the top encourages and supports employees early reporting when problems occur. Without early reporting, projects are less likely to remain on track and management may be unaware of a problem until it becomes significant.
[edit] Getting fit for the future
The highly fragmented nature of the sector and lack of training and innovation have been contributing to low productivity. Government can help to build confidence in the construction sector by showing more ambition and urgency in facilitating a commitment to a reliable pipeline of major infrastructure projects with guaranteed timings.
Businesses need to form partnerships with their local schools, colleges and universities to educate young men and women about the wide range of career opportunities available, creating a pipeline of future young talent.The stereotype of the hard hat-wearing construction worker needs to be retired and replaced with the image of the planner, architect, surveyor, engineer and skilled trades person.
[edit] About this article
This article was written by ice.org.uk Phil Joyce, The Orange Partnership and is based on the author's briefing article in the 172 CE4 issue of the ICE Civil Engineering Journal. The article previously appeared on the ICE website in October 2019 and can be accessed HERE.
More articles by ICA on Designing Buildings Wiki can be accessed HERE.
[edit] Related articles on Designing Buildings Wiki
- Auction theory.
- Best value.
- Bid writer.
- Competitive tender.
- E-tendering.
- Estimator.
- Form of tender.
- Game theory.
- Initial cost appraisal.
- Invitation to tender.
- Pre-tender estimate.
- Procurement route.
- Relationship management.
- Tender documentation.
- Tender evaluation.
- Tender process.
- Winning work in the construction industry.
- Zone of possible agreement.
Featured articles and news
About the 5 Percent Club and its members
The 5% Club; a dynamic movement of employers committed to building and developing the workforce.
New Homes in New Ways at the Building Centre
Accelerating the supply of new homes with MMC.
Quality Planning for Micro and Small to Medium Sized Enterprises
A CIOB Academy Technical Information sheet.
A briefing on fall protection systems for designers
A legal requirement and an ethical must.
CIOB Ireland launches manifesto for 2024 General Election
A vision for a sustainable, high-quality built environment that benefits all members of society.
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Comments
Specifying sustainable requirements.
Designers determine quality and sustainability initially through their specifications. The most efficient contractor at fulfilling those specifications exactly delivers the best value and is also the most sustainable. So, least cost equates to best value if the designers specify correctly.