Main types of planning permission
Contents |
[edit] Introduction
Planning permission is the legal process of determining whether proposed developments should be permitted. Responsibility for planning lies with local planning authorities (usually the planning department of the district or borough council). The legislation, policy and guidance that underpins planning in England can be found on the government's National Planning Practice Guidance website.
Other than permitted developments, (which are considered to have insignificant impact), all developments require planning permission. The Town and Country Planning (General Permitted Development) Order 1995 sets out details for developments that might be permitted without requiring a planning application.
There are three main types of planning permission:
- Outline
- Reserved matters
- Full planning (or detailed planning) permission.
[edit] Outline
Outline planning permission is an application for undertaking a development in principle. The applicant can use it to find out whether their proposed development is likely to be approved by the planning authority before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage (see below).
For more information see: Outline planning application
[edit] Reserved matters
Once outline planning consent has been obtained, the reserved matters stage is the follow-up which gives the applicant the opportunity to provide (usually within three years) more detail, including:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed significantly.
For more information see: Reserved matters.
[edit] Full planning (or detailed planning) permission
Where alteration or erection of buildings (or a change of use) is required, full planning permission is the most widely used option. It is made for developments that include building, engineering or other works, in, on, over or under land, or the making of any material change in the use of any buildings or other land.
A full planning application is made in detail, in one go – with no preliminary or outline stages – and consent, if granted, is for a limited time period. If the development does not begin within this period, the applicant must apply for a renewal of limited permission.
For more information see: Detailed planning application.
[edit] Others
Other types of planning consent that might be required include:
- Listed building consent
- Advertisement consent
- Lawful Development Certificate
- Prior approvals
- Removal/variation of conditions
- Discharge of conditions
- Consent under Tree Preservation Orders
- Notification of proposed works to trees in conservation areas
- Application for non-material amendments
[edit] Related articles on Designing Buildings Wiki
- Approved documents.
- Approved inspector.
- Building codes.
- Building control body.
- Building control performance standards.
- Building notice.
- Building Regulations Advisory Committee (BRAC).
- Building regulations completion certificate.
- Building regulations inspection.
- Building warrant (Scotland).
- Do the building regulations apply to existing buildings?
- Failure to comply with the building regulations.
- Full plans.
- How long it takes to get building regulations approval and how long it lasts.
- Independent review of the building regulations and fire safety.
- Planning permission.
- Scottish building standards.
- Standard Assessment Procedure.
- Statutory approvals.
- Statutory authorities.
- The Building Act.
- The difference between planning permission building regulations approval.
- Welsh building regulations.
- What approvals are needed before construction begins.
Featured articles and news
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
A dynamic brand built for impact stitched into BSRIA’s building fabric.