Sectional completion in construction contracts
Sectional completion refers to a provision within construction contracts allowing different completion dates for different sections of the works. This is common on large projects that are completed in sections, allowing the client to take possession of the completed parts whilst construction continues on others.
Sectional completion differs from partial possession in that it is pre-planned and defined in the contract documents.
If sectional completion is required, it must be an express term of the contract, and reflected by the fact that there are multiple completion dates rather than just one. The extent of each section must be clearly defined and liquidated damages, and the amount of retention that will be released must be specified for each section. There may also need to be clarification of how extension of time provisions will be applied if, for example, delays to one section of the works have a knock-on effect on other sections (the cascade effect).
In procedural terms, sectional completion is similar to normal completion and follows the usual handover procedures (see handover to client). However, some work within the section may remain outstanding, such as the completion of commissioning, operation and maintenance manuals and as built drawings, which will cross all sections.
It may exclude mechanical and electrical service systems which are reliant on total completion before they can be properly tested and commissioned. This means that their needs to be an agreed protocol for re-entry into completed sections for the contractors to complete outstanding work.
Sectional completion requires particular care to be taken regarding:
- Difficulties with logistics on site when different sections are in the possession of different parties.
- The protection of completed sections from ongoing work.
- The provision of appropriate insurance at all times for all sections.
- The adoption of appropriate health and safety measures to deal with risks resulting from occupation of areas adjacent to, or only accessible through ongoing construction works.
- The provision of appropriate security measures.
The consequences of sectional completion are that
- Half of the retention is released for that section.
- The Rectification Period begins for that section,
- The contractor’s responsibility for insuring the works (if applicable) ends for that section.
- The contractor’s liability for liquidated damages ends for that section.
- The employer is now responsible for any damages to the works for that section.
[edit] Related articles on Designing Buildings Wiki
- Building completion.
- Completion.
- Defects liability period.
- Defects.
- Difference between practical completion and partial possession.
- Early use.
- Extension of time.
- Handover to client.
- Liquidated damages.
- Loss and expense.
- Migration strategy.
- Occupation.
- Partial possession.
- Performance in use.
- Phased construction works.
- Possession.
- Post occupancy evaluation.
- Practical completion.
- Retention.
- Soft landings.
- Topping out.
- Work-to-complete list.
Featured articles and news
The restoration of the novelist’s birthplace in Eastwood.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.
Construction contract awards remain buoyant
Infrastructure up but residential struggles.
Home builders call for suspension of Building Safety Levy
HBF with over 100 home builders write to the Chancellor.
CIOB Apprentice of the Year 2024/2025
CIOB names James Monk a quantity surveyor from Cambridge as the winner.
Warm Homes Plan and existing energy bill support policies
Breaking down what existing policies are and what they do.
Treasury responds to sector submission on Warm Homes
Trade associations call on Government to make good on manifesto pledge for the upgrading of 5 million homes.
A tour through Robotic Installation Systems for Elevators, Innovation Labs, MetaCore and PORT tech.
A dynamic brand built for impact stitched into BSRIA’s building fabric.
BS 9991:2024 and the recently published CLC advisory note
Fire safety in the design, management and use of residential buildings. Code of practice.
Comments
Hi
I note sectional completion may not include the completed M&E or other element etc depending on how it is detailed in the contract docs.
What about partial possession (which I know is not preplanned) . Can partial possession cert be issued of there are still outstanding issues such as M&E, fire alarm etc.
Presumably not because it has to be complete ?
Niall
Question
what are the item we need to compile in sectional completion?
how was the
format of sectional completion?
how to describe it is sectional completion
when we want to give them it is sectional completion? or how to make sectional
completion certificate? is it like handover? do we need to produce as built
drawing as per hand over?
Answer --designing buildings 08:19, 30 June 2013 (BST)
This project is under construction. Certain section is completed. Can we make sectional completion even there is not stated sectional completion in the document contract. Does it wrong contractually?
Sectional completion is agreed before the contract is entered into. Partial possession or early use can be agreed whilst the contract is running.