Permit to work for construction
Permit to work (PTW) systems are formal procedures used to control activities that are considered high-risk. Permits only allow authorised personnel to perform those activities at specified times and in a way set out in the permit and referenced documents.
A permit to work might be required for activities such as:
- Electrical works.
- Hot works.
- Excavation.
- Lone working.
- Lifting operations.
- Work in confined spaces.
- Work to high risk spaces such as laboratories, or industrial plant.
- Work at height.
- Work to roofs.
- Temporary works.
- Work with asbestos.
- Demolition.
- Work to high pressure systems.
A permit to work system should:
- Only allow permits to be issued by authorised, competent personnel.
- Prevent high-risk work being carried out without a risk assessment having been undertaken.
- Consider whether any other work will impact on, or be impacted by, the permitted work.
- Ensure control measures and supervision are in place.
- Ensure method statements and emergency procedures are prepared.
- Ensure work is checked and returned to a safe state.
- Provide information to other parties that might be affected by the work.
- Include a system for handing back and cancelling permits.
Permits should:
- Describe the work and its location.
- Provide information about foreseeable risks.
- Provide information necessary for working safely.
- Set out requirements for personal protective equipment.
- Set out the time when the work can be carried out.
- Provide information about other permits.
Issuing permits to work can be a complicated and time-consuming process and so adequate notice should be given before a permit to work is required.
Permit to work systems do not in themselves make activities safer, this is only possible through the implementation of the correct procedures. It is important therefore that systems not box-ticking exercises, that they are explained at site inductions and that they are continuously monitored, reviewed and kept up to date.
NB BG 87/2024, Useful Information Guide, written by Chin Hang “Kay” Lam and published by BSRIA in 2024, defines a Permit-to-Work system as: ‘A documented management system that includes specific processes to record and authorise tasks to be carried out by designated parties, including employees and contractors, so that they are aware of their risks and responsibilities.’
[edit] Related articles on Designing Buildings
- Asbestos.
- CDM.
- Demolition.
- Gangmaster.
- Health and Safety.
- Method statement.
- Permit.
- Personal protective equipment
- Risk assessment.
- Safe2Torch.
- Site induction.
- Site records and registers.
[edit] External references
Featured articles and news
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.