Performance bond for construction
A performance bond (or performance security) is commonly used in the construction industry as a means of insuring a client against the risk of a contractor failing to fulfil contractual obligations to the client. Performance bonds can also be required from other parties to a construction contract.
Whether or not a performance bond is required will depend, in the main, on the perceived financial strength of the party bidding to win a contract, as the most common concern relates to a contractor becoming insolvent before completing the contract. Where this occurs the bond provides compensation guaranteed by a third party up to the amount of the performance bond.
Bonds are typically set at 10% of the contract value. This compensation can enable the client to overcome difficulties that have been caused by non-performance of the contractor such as, for example, finding a new contractor to complete the works.
Bonds can be 'on demand' or 'conditional', with conditional bonds requiring that the client provides evidence that the contractor has not performed their obligations under the contract and that they have suffered a loss as a consequence.
The obligation for the contractor to provide the client with a bond is set out in the tender documents. The choice of bondsman and terms with regard to cost falls entirely to the contractor who secures it prior to the start of work. From a client viewpoint it is wise to stipulate that the bond stays in place until the end of the defects liability period when the final certificate is issued.
Bonds can be issued either by an insurance company or by a bank, and the cost of the bond is usually borne by the contractor (albeit, this is likely to be reflected in the contractor's tender price). The cost of the bond gives the client a good guide as to the credit worthiness and reputation of the contractor in the bond market, which will view each contractor differently in respect of its history, management and financial health.
Strictly speaking, the bond is a guarantee and as such is a contingent liability in regard to the contractor's balance sheet. A smaller contractor might face a limit on how many bonds it can take out.
The contractor sends the bond document to the beneficiary, i.e. the client who holds it until the end of the defects liability period.
The bond is related to the contract conditions and the courts take a view that the bondsman has little protection against adverse risk. So it is wise to seek the bondsman's consent before acting outside the contract conditions, for example by paying the contractors in advance of work undertaken to ease its cash flow difficulties. Such conduct could jeopardise a subsequent claim on the bond.
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Bid bond.
- Bonds.
- Bonds v guarantees.
- Bondsman.
- Comfort letter.
- Contingency.
- Construction contract.
- Contractor.
- Collateral warranties.
- Contractors' all-risk insurance.
- Escrow.
- Miller Act.
- Parent company guarantee.
- Performance.
- Procurement.
- Professional indemnity insurance.
- Professional Indemnity Insurance clause in conditions of engagement
- Retention.
- Retention bond.
- Retention held in trust fund.
- Surety.
- Tender documentation.
- Warranty.
- Workmanlike manner.
- Zero-coupon bond.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Comments
Nationwide Sureties provide Performance Bonds for Construction Contracts across the country and internationally to help bring new developments to fruition.