Payment due date in the construction industry
The Housing Grants, Construction and Regeneration Act (also known as the Construction Act) includes provisions to ensure payments are made promptly throughout the supply chain.
Section 110A(6) of the Act defines the “payment due date” as “…the date provided for by the contract as the date on which the payment is due”.
The payer must issue a payment notice within five days of the due date for payment, even if no amount is due, setting out the sum that the payer considers to be or to have been due at the payment due date, and the basis on which that sum is calculated. Alternatively, if the contract allows, the payee may make an application for payment, which is treated as if it is the payment notice. The payer must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
The contract must also provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. The payer must pay the notified sum on or before the final date for payment.
If payment is not made on or before the final date for payment the payee can give notice under Section 112 of the Act to suspend performance of the contract.
Under the Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the assessment date or the making of a claim by the payee. The final date for payment is 17 days after the date that payment became due.
Under the Late Payment of Commercial Debts (Interest) Act 1998 the payment due date is referred to as an 'agreed payment day'.
[edit] Related articles on Designing Buildings
Featured articles and news
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
ECA progress on Welsh Recharging Electrical Skills Charter
Working hard to make progress on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Comments
Thank you for the comments below. The article has been updated.
I cannot agree with the article.
The 'payment due date' and the 'final date for payment' should not be confused.
Please refer to the defiinition contained in Section 110A(6) of the Housing Grants, Construction and Regeneration Act 1996 'payment due date' means 'the date on which the payment is due' and not the date on which the payment process is invoked. The 'payment due date' is the date by which the payee should receive payment.
The 'final date for payment' is the date after which the payee can give notice under Section 112 of the Act to suspend performance of the contract because the payee has not received payment.
Under The Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the [assessment date] or the making of a claim by the payee. The 'final date for payment' is 17 days after the date that payment became due.
Moreover, under the Late Payment of Commercial Debts (Interest) Act 1998 the 'payment due date' and not the 'final date for payment' will be an 'agreed payment day' from which statutory interest will begin to run.