Payment due date in the construction industry
The Housing Grants, Construction and Regeneration Act (also known as the Construction Act) includes provisions to ensure payments are made promptly throughout the supply chain.
Section 110A(6) of the Act defines the “payment due date” as “…the date provided for by the contract as the date on which the payment is due”.
The payer must issue a payment notice within five days of the due date for payment, even if no amount is due, setting out the sum that the payer considers to be or to have been due at the payment due date, and the basis on which that sum is calculated. Alternatively, if the contract allows, the payee may make an application for payment, which is treated as if it is the payment notice. The payer must issue a pay less notice if they intend to pay less than the amount set out in the payment notice, setting out the basis for its calculation.
The contract must also provide for a final date for payment in relation to any sum which becomes due. The parties are free to agree how long the period is to be between the date on which a sum becomes due and the final date for payment. The payer must pay the notified sum on or before the final date for payment.
If payment is not made on or before the final date for payment the payee can give notice under Section 112 of the Act to suspend performance of the contract.
Under the Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the assessment date or the making of a claim by the payee. The final date for payment is 17 days after the date that payment became due.
Under the Late Payment of Commercial Debts (Interest) Act 1998 the payment due date is referred to as an 'agreed payment day'.
[edit] Related articles on Designing Buildings
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.
Comments
Thank you for the comments below. The article has been updated.
I cannot agree with the article.
The 'payment due date' and the 'final date for payment' should not be confused.
Please refer to the defiinition contained in Section 110A(6) of the Housing Grants, Construction and Regeneration Act 1996 'payment due date' means 'the date on which the payment is due' and not the date on which the payment process is invoked. The 'payment due date' is the date by which the payee should receive payment.
The 'final date for payment' is the date after which the payee can give notice under Section 112 of the Act to suspend performance of the contract because the payee has not received payment.
Under The Scheme for Construction Contracts, if a construction contract fails to provide an adequate mechanism for determining when a payment becomes due, the payment shall become due, that is, payable on the later of 7 days after the [assessment date] or the making of a claim by the payee. The 'final date for payment' is 17 days after the date that payment became due.
Moreover, under the Late Payment of Commercial Debts (Interest) Act 1998 the 'payment due date' and not the 'final date for payment' will be an 'agreed payment day' from which statutory interest will begin to run.