Operational rate estimating
Contents[hide] |
[edit] Introduction
Operational rate estimating is a method used to calculate building costs. In operational rate estimating a distinct parcel of work is priced as a package. This is as opposed to projects where each unit of the bill of quantities are priced individually.
The estimator will still need to calculate all the individual items that are required in unit rate estimating , such as labour, plant and materials, but the key difference in operational estimates is that the estimator views a section of the work as a whole rather than as a set of separate items.
[edit] Operational Rate
Operational rate estimating is commonly used in the civil engineering industry. This is generally due to the larger quantities involved in civil engineering projects. The plant and machinery required in civil engineering works can also play a more significant role in the project. Operational estimating is preferred in plant-dominated projects.
Operational rate estimating can also be be used for pricing in design and build contracts where the contractor is responsible for their own pricing methods and a bill does not have to be produced.
The estimator will calculate all the resources needed for parts of the construction packages together rather than in isolation. Operational estimating will involve forecasting the cost of completing a construction operation, which may consist of many bill items.
Operational estimating will require a completed:
It is usually beneficial for the estimator to work alongside the operational teams to prepare the resource schedules and programmes as they may require comparative estimates or cost alternatives to help adopt the most suitable approach and achieve value for money.
Typical packages in operational estimating are:
[edit] Related articles on Designing Buildings Wiki
- All-in rates.
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Capital.
- Contract sum.
- Cost control.
- Cost engineering.
- Cost information.
- Cost plan.
- Elemental cost plan.
- Estimating
- Initial cost appraisal.
- Measurement.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender cost.
- Unit rate estimating.
[edit] External references
- Quantity Surveyor’s Pocket Book by Duncan Cartlidge.
Featured articles and news
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.