Operational rate estimating
Contents |
[edit] Introduction
Operational rate estimating is a method used to calculate building costs. In operational rate estimating a distinct parcel of work is priced as a package. This is as opposed to projects where each unit of the bill of quantities are priced individually.
The estimator will still need to calculate all the individual items that are required in unit rate estimating , such as labour, plant and materials, but the key difference in operational estimates is that the estimator views a section of the work as a whole rather than as a set of separate items.
[edit] Operational Rate
Operational rate estimating is commonly used in the civil engineering industry. This is generally due to the larger quantities involved in civil engineering projects. The plant and machinery required in civil engineering works can also play a more significant role in the project. Operational estimating is preferred in plant-dominated projects.
Operational rate estimating can also be be used for pricing in design and build contracts where the contractor is responsible for their own pricing methods and a bill does not have to be produced.
The estimator will calculate all the resources needed for parts of the construction packages together rather than in isolation. Operational estimating will involve forecasting the cost of completing a construction operation, which may consist of many bill items.
Operational estimating will require a completed:
It is usually beneficial for the estimator to work alongside the operational teams to prepare the resource schedules and programmes as they may require comparative estimates or cost alternatives to help adopt the most suitable approach and achieve value for money.
Typical packages in operational estimating are:
[edit] Related articles on Designing Buildings Wiki
- All-in rates.
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Capital.
- Contract sum.
- Cost control.
- Cost engineering.
- Cost information.
- Cost plan.
- Elemental cost plan.
- Estimating
- Initial cost appraisal.
- Measurement.
- New Rules of Measurement.
- Order of cost estimate.
- Pre-tender estimate.
- Tender cost.
- Unit rate estimating.
[edit] External references
- Quantity Surveyor’s Pocket Book by Duncan Cartlidge.
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.