Mitigation in the construction industry
The term ‘mitigate’ means to make less severe or serious.
This can be important in the construction industry in a number of different circumstances.
- In relation to project delays, it refers to minimising the impact of the risk event (an event or cause of delay or disruption). For example, acceleration might be used to mitigate a delay. Where there is a claim for an extension of time, the contractor may be required to mitigate the delay and any resulting loss, even where the fault is not their own.
- In terms of losses incurred, it can refer to claimant's duty to mitigate their loss. A claimant will generally not be allowed to recover damage which could have been avoided had the claimant acted reasonably. For more information see: Mitigation of loss.
- In relation to planning policy, planning obligations or planning conditions might be used to mitigate or compensate for the negative impacts of a development. For more information see: Planning obligation and planning condition.
- In terms of risks, a contingency plan might be enacted to mitigate project risks, such as adverse weather, industrial disputes and so on. For more information see: Contingency plan.
Mitigation strategies might also be used in relation to:
- Environmental impact.
- Loss of habitat.
- Carbon emissions.
- Flood protection.
- Duty to warn.
A handbook on environmental impact assessment, 4th edition, published by Scottish Natural Heritage in 2013, suggests that:
These are the measures taken to avoid, cancel or reduce adverse impacts of a project. They are:
- Avoidance measures: Designed to avoid or eliminate any adverse impacts arising in the first place, including alternative or ‘do nothing’ options;
- Cancellation measures: Designed to nullify or cancel out any adverse effects of a project before adverse effects are felt;
- Reduction measures: Designed to minimise or at least reduce adverse impacts remaining after avoidance and cancellation measures have been applied to a project.
Culvert, screen and outfall manual, (CIRIA C786) published by CIRIA in 2019, suggests that the mitigation hierarchy is typically:
NB Global Warming of 1.5 ºC, Glossary, published by the Intergovernmental Panel on Climate Change (IPCC) in 2018, defines mitigation (of climate change) as: ‘A human intervention to reduce emissions or enhance the sinks of greenhouse gases.’
[edit] Related articles on Designing Buildings
- Consequential loss.
- Planning condition.
- Planning obligation.
- Contingency plan.
- Risk.
- Environmental impact assessment.
- Relevant event.
- Extension of time.
- Duty to warn in construction.
[edit] External references
- Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
Featured articles and news
Download your free guide.
Four new types of prior approval for solar developments
Online Planning Portal application types from 5 September.
Election fails to spark construction industry revival
Contract awards and planning; post election.
Making diversity and inclusion easy for SMEs
The CIOB tool for companies with limited resources.
Sustainable Futures: Redefining Retrofit for Net Zero Living
BSRIA Briefing 2024, initial speakers announced.
Looking back at the UK's first Passivhaus leisure centre
Reflections on St Sidwell’s Point with CIAT.
A-Level results and electrical apprenticeships
Electrical Skills Index highlights areas with skills shortages.
One of the world's more unusual drive-throughs.
A quick introduction.
Hadrian's Wall Path and the national trails
The trails are heritage assets in their own right.
Articles on timely advice and hydraulic lime.
Building Designers Association of Australia
CIAT and BDAA sign Memorandum of Understanding.
Built Environment Inclusive partners issue statement committed to inclusion.
Building regulation requirements can have unintended consequences.
CIOB announces 2024/25 vice president
Sustainability champion Professor Saul Humphrey.
Accelerating towards a net-zero built environment.