Just in time
Contents |
[edit] Introduction
Just-in-time (JIT) is a production and delivery system developed in Japan in the 1960s and 1970s that ensures materials and components are delivered from the manufacturer to the production site at exactly the right moment to enable immediate use in the production process.
The right materials are supplied in the right order, in the right amount at the right time. The deliveries tend to be regular and in small amounts. The process is also known as ‘Just-in-time production’ and the ‘Toyota Production System’. In recent years the term has been used synonymously with lean manufacturing.
JIT can be critical for some manufacturing processes (such as cars) as it greatly simplifies logistics: components are delivered directly to the production floor so manufacturers do not have to store or warehouse them (or else they only require minimal storage), thereby saving space, time and costs – and making for a more efficient process overall.
Known as a ‘pull’ process, the JIT concept was developed in Japan and is used by the Toyota car company which uses ‘Kanban’ (sign) boards for ordering parts: when a part has been used, the Kanban is taken off the packaging and sent back to the preceding process as an order for an additional item. This sign-based scheduling system signals the need to replenish the product and delivery and maintains production at an optimum level.
Drawbacks of the system are that it works best when production numbers are constant. Also, it is vital that every part fits as it is intended to first time round as there are no other parts available at that time. In addition, if a problem or minor disruption occurs in the supply chain, the manufacturer has no stocks to fall back on and could see production halt at short notice.
[edit] Just-in-time in construction
Products and materials constitute a huge part of the construction process and it has been estimated that greater efficiencies in logistics can reduce waste in construction by up to 35%. Many projects can benefit from JIT delivery and, given the often congested nature of construction sites, rewards similar to those seen in manufacturing industry may be possible.
A prime example is ready-mixed concrete: the perishable nature of this material means that having been mixed to the customer’s exact specification, it must be delivered at the right time, in the right quantity (and at the right specification) to allow pouring before setting takes place. Another example is windows or glazed cladding panels, where on-site storage would necessitate extensive inventory facilities and potential risks of product damage.
JIT in construction has also been referred to as ‘lean construction’ – an adaptation of lean production techniques.
[edit] Just in time delivery / logistics
The BIM Overlay to the RIBA Outline Plan of Work, published by the RIBA in 2012 defined just in time (JIT) delivery, or just in time logistics as: '..receiving raw materials,
products and parts in the factory and then on site as they are needed, rather than days or even weeks before. This allows businesses to significantly cut inventory costs by having fewer unnecessary supplies on hand, and means they have far less material to store and handle. Where buffer stocks are considered necessary (e.g. as a result of a risk analysis), they are specified in terms of time periods linked to the assembly plan (e.g. one day of manufacturing).'
[edit] Related articles on Designing Buildings Wiki
- Time of the essence in construction contracts
- Advanced manufacturing.
- Block planning.
- Design for Manufacture and Assembly (DfMA).
- Egan report.
- Green supply chain management.
- Integrated project delivery (IPD).
- Kanban.
- Lean construction.
- Lean construction - a quality perspective.
- Logistics management.
- Off site materials.
- Flying factory.
- Mean lean green.
- Regularly and diligently.
- Site storage.
- Time at large.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.