Final certificate for construction contracts
Contents |
[edit] Introduction
The final certificate is certification by the contract administrator that a construction contract has been fully completed. It is issued at the end of the defects liability period and has the effect of releasing all remaining money due to the contractor, including any remaining retention.
The value of the final certificate will be based on the final account agreed by the cost consultant and the contractor. This means that all patent defects must have been remedied, all adjustments to the contract sum must have been agreed and all claims settled.
Where proceedings have been commenced in relation to a dispute, the conclusiveness of the final certificate is subject to the findings of those proceedings. In addition, the final certificate itself can be disputed (usually within 28 days). Adjudication, arbitration or other proceedings may then be necessary to resolve the dispute. The final certificate is then only conclusive in relation to matters that are not disputed.
If the client intends to pay a different amount from that shown on the certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice - see Housing Grants, Construction and Regeneration Act for more information).
[edit] Alternative procedures
In design and build contracts (such as Joint Contracts Tribunal (JCT) DB 16) the final certificate may be described as the final statement.
In construction management contracts, where there are a number of trade contracts, final statements are issued for each trade contract. Once final statements have been issued for each trade contract, the construction manager co-ordinates preparation of the final report and issues the final certificate for the whole project.
There is a similar procedure on management contracts, where final certificates are issued by the management contractor for each individual works contract, and then once all works contracts have received a final certificate, the management contractor provides the client's contract administrator (or cost consultant) with information allowing them to calculate the prime cost (the cost of the works contracts) and a final certificate is issued to the management contractor.
[edit] Alternative meaning
Rather confusingly, the term 'final certificate' can also refer to a completion certificate issued by a building control body in relation to the building regulations.
Manual to the Building Regulations: A code of practice for use in England, published by HM Government in July 2020, states: ‘Final certificate refers to the certificate issued by the approved inspector to the person carrying out the work and the local authority and confirms that the work in the initial notice is complete and that the approved inspector is satisfied that it complies with the relevant requirements of the Building Regulations.’
See Building regulations completion certificate for more information.
[edit] Related articles on Designing Buildings Wiki
- Building regulations completion certificate.
- Certificates in the construction industry.
- Contract administrator.
- Defects liability period.
- Final account.
- Housing Grants, Construction and Regeneration Act.
- Retention.
- Interim certificates.
- Sectional completion.
- Topping out.
- What is a final account.
- Work-to-complete list.
Featured articles and news
The benefits of writing articles for your organisation
How to create a profile for your organisation and publish for free.
No Falls Week. The importance of safe working at height
What to expect and what is on offer to avoid accidents.
Scottish Government action to reach net-zero targets
Retrofit expert group highlight critical actions needed.
A forward thinking, inclusive global community of members.
From engineered product life-spans, to their extension.
Circular economy in the built environment
A brief description from 2021. Where are we now?
Mental Health Awareness Week with ABS
Architects Benevolent Society programme of activity.
CLC publishes domestic retrofit competency framework
Roadmap of Skills for net zero.
May 13-19: Moving more for our mental health.
Understanding is key to conservation.
Open industry engagement survey seeks responses
Institutions and the importance of engagement.
National Retrofit Hub unveils new guide
Digital Building Logbooks and Retrofit: An Introduction.
Enhancing construction site reporting efficiency
Through digitisation and the digital revolution.
Noise in the built environment
BSRIA guide TG 20/2021.
17,000 people suffer conditions as a result of exposure to excessive noise at work.
Turning down the noise: Auditory health
A pervasive risk with far-reaching consequences.
Getting the most out of heat pumps and heating
How heat pumps work and how they work best.
Electrotechnical excellence, now open for entries.
Comments
What does a 'Part Final Certificate' mean? Does it mean for the specified works it is fully complete (but there are other works as part of the application) Or that the specified works are part complete?
This might relate to a final certificate for part of the works - ie where there is partial possession or sectional completion - see the comments at the end of those articles.
However, the specific term 'part final certificate' is more commonly used in relation to building regulations approvals.