Dilapidations protocol
Dilapidations are breaches of leases due to the condition of the property being leased, either during or at the end of the lease period. This may result from mistreatment of the property or poor or absent maintenance or repairs that are required by the lease. Further work may also be required at the end of a lease to reinstate alterations that have been made to the property by the tenant.
Dilapidations are a common cause of dispute and if the parties fail to reach agreement, disputes may come before the courts.
The ‘dilapidations protocol’ (The ‘Pre-Action Protocol for Claims for Damages in Relation to the Physical State of Commercial Property at Termination of a Tenancy’) is a pre-action protocol for commercial property available from the Ministry of Justice.
The first edition of the dilapidations protocol, was introduced in 2002 by the Property Litigation Association (PLA), endorsed by the Royal Institution of Chartered Surveyors (RICS). The Civil Procedure Rule Committee agreed that it should be adopted under the Civil Procedure Rules (CPR) in 2011 and it came into force on 1 January 2012.
It describes the conduct the court expects the parties to follow before commencing proceedings in relation to a dilapidations claim. It sets out a process and timetable for the exchange of information, and establishes standards for the content and quality of schedules of dilapidations and quantified demands.
The Ministry of Justice states that, ‘Where the court considers non-compliance, and the sanctions to impose where it has occurred, it will, amongst other things, be concerned about whether the parties have complied in substance with the relevant principles and requirements and is not likely to be concerned with minor or technical shortcomings’.
The Ministry of Justice state that the objectives of the dilapidations protocol are to:
- Encourage the exchange of early and full information about the dispute.
- Enable the parties to avoid litigation by agreeing a settlement before proceedings are commenced.
- Support the efficient management of proceedings where litigation cannot be avoided.
There is a separate Pre-Action Protocol for Housing Disrepair cases.
NB Dilapidations in England And Wales, 7th Edition, was published on 31 August 2016 by the Royal Institution of Chartered Surveyors (RICS), it defines the dilapidations protocol (‘the Protocol’) as the: ‘…pre-action protocol for claims for damages in relation to the physical state of commercial property at the termination of a tenancy (applicable to terminal dilapidations disputes).’
[edit] Related articles on Designing Buildings
- Alternative dispute resolution.
- Arbitration
- Betterment.
- Break clauses in leases.
- Civil procedure rules.
- Defects.
- Dilapidations.
- Disputes.
- Lease Negotiations - Tenants Checklist.
- Licence for Alterations for Apartment.
- Licence to alter.
- Payment for dilapidations.
- Quantified demand.
- Rent-free period.
- Rent in administration.
- Rent review.
- Sample retail lease.
- Schedule of dilapidations.
- Scott schedule.
- Supersession.
[edit] External references
- TCC, Court Guide Second Edition Issued 3rd October 2005, third revision with effect from 3 March 2014, HM Courts and Tribunals Service.
- Ministry of Justice, Dilapidations Protocol.
- Ministry of Justice, Pre-Action Protocol for Housing Disrepair.
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.