CDM 2007 Health and safety file
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 health and safety file, see Health and safety file.
On projects that are notifiable to the HSE, (that is, the works are likely to last longer than 30 days or involve more than 500 person days of construction), the Construction (Design and Management) Regulations (CDM regulations) require that the CDM co-ordinator:
'...prepare, where none exists, and otherwise review and update a record (“the health and safety file”) containing information relating to the project which is likely to be needed during any subsequent construction work to ensure the health and safety of any person, including the information provided in pursuance of regulations 17(1), 18(2) and 22(1)(j).',
At the end of the construction phase, the CDM co-ordinator must pass the health and safety file to the client (NB where there is partial possession or sectional completion of the works, the health and safety file may be required before all the works are complete in order to inform ongoing work).
Before work starts on site the CDM co-ordinator should discuss with the client the scope, format, structure and content of the health and safety file, as well as who should provide information, and when. There may be separate files for different premises, or one overall file, and the file can be combined with the building log book, or building owner's manual. However, the health and safety information must be easy to find, if a file is created that simply contains all information about the building then genuinely important safety issues may be overlooked.
The health and safety file need only include information important to enable future construction work to be carried out safely (including cleaning, maintenance, refurbishment, alterations and eventual demolition). It should contain content that is useful and it should be in proportion to the risks involved in the project.
It does not need to include information about the construction process (which may be included in the construction phase plan), unless it may affect future works. It does not need to include contractual information, pre-construction information or information about the normal operation of the completed structure (which may be included in the building owners manual or the building log book, ref Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice page 60).
The contents of the health and safety will vary depending on the nature of the works being carried out, however, it may contain:
- A description of the project.
- A description of any residual hazards that should be managed.
- The structural principles of the design.
- Identification of any hazardous materials used.
- Procedures for the removal or dismantling of installed plant and equipment.
- Information about cleaning and maintenance equipment.
- A description of significant services and their location.
- Information and as-built drawings of the structure, plant and equipment.
The health and safety file must be kept up to date, and clients must ensure that the file is available for inspection in the event future work. If work is done to premises where a health and safety file already exists, the health and safety file should be updated if necessary (and any gaps filled), even if the work is not notifiable.
The health and safety file is normally kept for the lifetime of the building, meaning that it should be passed on to the new owners if the building is sold, and the new owners should be informed of its purpose and importance.
There are no restrictions to the format that it has to be kept in, but it would be wise to ensure it is backed up.
If the premises, or part of it are leased, then the health and safety file to must be made available to the leaseholder. If there are multiple leaseholders, then those parts of the health and safety file relevant to the part of the building leased by each leaseholder must be made available to them. In multi-occupancy situations, for example where a housing association owns a block of flats, the owner should keep and maintain the file, but ensure that individual flat occupiers are supplied with health and safety information concerning their home.
[edit] Related articles on Designing Buildings Wiki
- Building log book.
- Building owner's manual.
- CDM.
- CDM co-ordinator.
- CDM planning period.
- Construction phase plan.
- Defects liability period.
- Demolition.
- Health and safety.
- Notify HSE (Form F10).
- Personal protective equipment.
- Pre-construction information.
- Principal contractor.
- Soft landings.
- Technical guide.
[edit] External references
- Full copy of the CDM regulations.
- Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice. The main headings for the Health and Safety Files are included in Appendix 3.
- Regulation 10 (Pre construction information).
Featured articles and news
HE expands finance alliance to boost SME house building
Project follows on from Habiko public-private place making pension partnership for affordable housing delivery.
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
How orchards can influence planning and development.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.