CDM 2007 Health and safety file
The CDM regulations were revised in 2015 and this article is no longer current. It is provided here for historical reference only.
For information about the CDM 2015 health and safety file, see Health and safety file.
On projects that are notifiable to the HSE, (that is, the works are likely to last longer than 30 days or involve more than 500 person days of construction), the Construction (Design and Management) Regulations (CDM regulations) require that the CDM co-ordinator:
'...prepare, where none exists, and otherwise review and update a record (“the health and safety file”) containing information relating to the project which is likely to be needed during any subsequent construction work to ensure the health and safety of any person, including the information provided in pursuance of regulations 17(1), 18(2) and 22(1)(j).',
At the end of the construction phase, the CDM co-ordinator must pass the health and safety file to the client (NB where there is partial possession or sectional completion of the works, the health and safety file may be required before all the works are complete in order to inform ongoing work).
Before work starts on site the CDM co-ordinator should discuss with the client the scope, format, structure and content of the health and safety file, as well as who should provide information, and when. There may be separate files for different premises, or one overall file, and the file can be combined with the building log book, or building owner's manual. However, the health and safety information must be easy to find, if a file is created that simply contains all information about the building then genuinely important safety issues may be overlooked.
The health and safety file need only include information important to enable future construction work to be carried out safely (including cleaning, maintenance, refurbishment, alterations and eventual demolition). It should contain content that is useful and it should be in proportion to the risks involved in the project.
It does not need to include information about the construction process (which may be included in the construction phase plan), unless it may affect future works. It does not need to include contractual information, pre-construction information or information about the normal operation of the completed structure (which may be included in the building owners manual or the building log book, ref Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice page 60).
The contents of the health and safety will vary depending on the nature of the works being carried out, however, it may contain:
- A description of the project.
- A description of any residual hazards that should be managed.
- The structural principles of the design.
- Identification of any hazardous materials used.
- Procedures for the removal or dismantling of installed plant and equipment.
- Information about cleaning and maintenance equipment.
- A description of significant services and their location.
- Information and as-built drawings of the structure, plant and equipment.
The health and safety file must be kept up to date, and clients must ensure that the file is available for inspection in the event future work. If work is done to premises where a health and safety file already exists, the health and safety file should be updated if necessary (and any gaps filled), even if the work is not notifiable.
The health and safety file is normally kept for the lifetime of the building, meaning that it should be passed on to the new owners if the building is sold, and the new owners should be informed of its purpose and importance.
There are no restrictions to the format that it has to be kept in, but it would be wise to ensure it is backed up.
If the premises, or part of it are leased, then the health and safety file to must be made available to the leaseholder. If there are multiple leaseholders, then those parts of the health and safety file relevant to the part of the building leased by each leaseholder must be made available to them. In multi-occupancy situations, for example where a housing association owns a block of flats, the owner should keep and maintain the file, but ensure that individual flat occupiers are supplied with health and safety information concerning their home.
[edit] Related articles on Designing Buildings Wiki
- Building log book.
- Building owner's manual.
- CDM.
- CDM co-ordinator.
- CDM planning period.
- Construction phase plan.
- Defects liability period.
- Demolition.
- Health and safety.
- Notify HSE (Form F10).
- Personal protective equipment.
- Pre-construction information.
- Principal contractor.
- Soft landings.
- Technical guide.
[edit] External references
- Full copy of the CDM regulations.
- Managing health and safety in construction, Construction (Design and Management) Regulations 2007, Approved Code of Practice. The main headings for the Health and Safety Files are included in Appendix 3.
- Regulation 10 (Pre construction information).
Featured articles and news
Shortlist for the 2025 Roofscape Design Awards
Talent and innovation showcase announcement from the trussed rafter industry.
OpenUSD possibilities: Look before you leap
Being ready for the OpenUSD solutions set to transform architecture and design.
Global Asbestos Awareness Week 2025
Highlighting the continuing threat to trades persons.
Retrofit of Buildings, a CIOB Technical Publication
Now available in Arabic and Chinese aswell as English.
The context, schemes, standards, roles and relevance of the Building Safety Act.
Retrofit 25 – What's Stopping Us?
Exhibition Opens at The Building Centre.
Types of work to existing buildings
A simple circular economy wiki breakdown with further links.
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
The smart construction dashboard, as-built data and site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure Bill
An outline of the bill with a mix of reactions on potential impacts from IHBC, CIEEM, CIC, ACE and EIC.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.