Best endeavours v reasonable endeavours
Many construction industry practitioners will have been confronted with a contract which requires the parties to use 'best' or 'reasonable' endeavours in performing obligations under the contract. This apparently minor difference however presents a real risk to a party if they are unaware of the difference in legal interpretation between the two terms.
Evidently an obligation to use 'best endeavours' implies a higher degree of commitment to perform a particular task when compared to 'reasonable endeavours' but, as is often the case, it is only when a contract dispute arises and Court proceedings follow that the reality of the difference becomes apparent.
There are no clear definitions of these terms upon which reliance can be made but case law has held that best endeavours means, amongst other things:
- To leave no stone unturned.
- To do what is reasonably to be expected in the circumstances.
- Not to do anything that will jeopardise the commercial interests of the obligor.
An immediate and obvious difficulty is that the word “reasonably” appears in a definition of 'best' endeavours. Furthermore, case law has also used similar language in defining reasonable endeavours.
Behind these definitions lies an expectation of what might be done to ensure that these obligations are met.
In the case of best endeavours it may be the case that a party has to commit extra resources or spend additional funds in order to meet the obligation, even to the extent that it is commercially damaging to the party concerned. Where the obligation is reasonable it is unlikely that this degree of obligation would be applied by the Courts.
And when it comes to testing these definitions in Court a subjective approach is adopted for best endeavours whilst it is an objective one for reasonable endeavours.
For the purposes of the layman, however, one can point to certain more simple facts:
- Reasonable endeavours will be less onerous than best endeavours.
- If a contract sets out specific steps to be taken as part of a reasonable obligation, ensure that these steps are indeed carried out. This is regardless of commercial considerations.
This article was created by: --Martinc 14:11, 22 November 2014 (UTC)
[edit] Related articles on Designing Buildings Wiki
- Delict.
- Duty of care.
- Duty to warn.
- Fitness for purpose.
- Good faith.
- Good faith – good grief.
- Reasonable skill and care.
- Unreasonable.
[edit] Relevant case law
Featured articles and news
Local leaders gain new powers to support local high streets
High Street Rental Auctions to be introduced from December.
Infrastructure sector posts second gain for October
With a boost for housebuilder and commercial developer contract awards.
Sustainable construction design teams survey
Shaping the Future of Sustainable Design: Your Voice Matters.
COP29; impacts of construction and updates
Amid criticism, open letters and calls for reform.
The properties of conservation rooflights
Things to consider when choosing the right product.
Adapting to meet changing needs.
London Build: A festival of construction
Co-located with the London Build Fire & Security Expo.
Tasked with locating groups of 10,000 homes with opportunity.
Delivering radical reform in the UK energy market
What are the benefits, barriers and underlying principles.
Information Management Initiative IMI
Building sector-transforming capabilities in emerging technologies.
Recent study of UK households reveals chilling home truths
Poor insulation, EPC knowledge and lack of understanding as to what retrofit might offer.
Embodied Carbon in the Built Environment
Overview, regulations, detail calculations and much more.
Why the construction sector must embrace workplace mental health support
Let’s talk; more importantly now, than ever.
Ensuring the trustworthiness of AI systems
A key growth area, including impacts for construction.
Foundations for the Future: A new model for social housing
To create a social housing pipeline, that reduces the need for continuous government funding.
Mutual Investment Models or MIMs
PPP or PFI, enhanced for public interest by the Welsh Government.
Key points and relevance to construction of meeting, due to reconvene.