Liquidation in the construction industry
Contents |
[edit] Introduction
The term ‘insolvency' describes the inability of a debtor to pay its debts. In the United Kingdom, insolvent individuals are made 'bankrupt', while companies are put into 'liquidation' or 'administration'. In cases of administration, a key objective is to try to ensure the company survives, whereas in liquidation, the company will generally not survive.
Insolvency proceedings are administrative processes instigated by either the insolvent entity or one of their creditors to recover assets so for disposal, the proceeds of which are distributed to creditors.
The Insolvency Act 1986 sets out four types of procedures governing the affairs of insolvent companies:
- Company Voluntary Arrangements.
- Administration.
- Receivership (less common following the enactment of the Enterprise Act 2000).
- Winding up leading to liquidation.
[edit] Liquidation
A company may be wound up either by court order or voluntarily. A court may wind up a company on presentation of a petition on grounds such as being unable to pay its debts.
A company can be deemed unable to pay its debts for a number of reasons, including:
- A statutory demand for a debt being served on the company and the company failing to satisfy that debt within three weeks.
- A court judgment against it, where steps to enforce the judgment have been unsuccessful.
- It is proved that the company is unable to pay its debts.
- Its assets are less than its liabilities.
Where a winding up order is made, this has the effect of discharging all employees, ending any agency relationships, and dismissing the company’s directors.
A liquidator is appointed to dispose of the company’s assets to discharge its liabilities to creditors, with any surplus being passed to whomever is entitled to it. Liquidators hold wide powers, constituting the governing body of the company and the receiver of its assets. They are entitled to their own costs before proceeds are distributed to creditors.
Once the process is complete the company is dissolved, which means that it has ceased to exist.
[edit] Liquidation of the main contractor
Liquidation is less common that administration in the construction industry. In the case of Carillion in 2018, it is thought that liquidation was chosen as there were insufficient remaining funds to appoint an administrator. Contractually, the consequences are the same, treated simply as 'insolvency'.
Insolvency of contractors is relatively common due to the low margins that they typically operate with, the high risk of project costs increasing, and constant cash flow and late payment issues.
Signs that a contractor may be in difficulties can include:
- Inactivity, or a lack of materials or plant on site.
- Late payments.
- An increase in the number of disputes, claims and exaggerated claims.
- Requests for advance payment.
- Lack of response to communications.
Most contracts will allow employers to terminate the employment of the contractor in the event of contractor insolvency and to cease payment. Typically, the contract will also allow them to employ others to complete the works and to use plant, tools, equipment, materials, temporary buildings and so on to do so. However, the employer must be certain of the insolvency first, and may seek evidence to confirm the fact.
This still leaves the employer having to find a new contractor and this can be time consuming and expensive, with other prospective contractors knowing that the employer is in a weak negotiating position. They client may also need consent from funding bodies to replace the contractor.
There may also be issues about:
- The ownership of goods, materials and so on that the employer has paid for, but are not in possession of.
- Goods or materials that have been delivered to site but not fixed to the building or paid for (which suppliers may attempt to remove).
- Defects in the works that the contractor has not rectified.
- Latent defects that may not yet be apparent.
- Outstanding payments.
- Overpayment for work that has not been completed.
- Advance payments.
- Outstanding disputes.
The situation is complicated by the prevalence of sub-contracting in the industry. The employer's main contractual link to subcontractors is through the contractor, and this link is been broken by the insolvency. The employer may be protected to some extent by provisions such as collateral warranties and step in rights.
However, the complexity and extent of the supply chain means that the knock on effects of main contractor insolvency can be far reaching. This is exacerbated by the fact that late payment is rife, and so companies in the supply chain of the insolvent company might be owed very large sums of money that they may be unable to continue without.
Other provisions that might give the employer some protection from main contractor insolvency include:
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Carillion.
- Collateral warranties.
- Government procurement post-Carillion.
- Insolvency.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Parent company guarantees.
- Performance bonds.
- Project bank accounts.
- Retention of title.
- Retention.
- Step in rights.
- Vesting certificate.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.