Alcatel period
Contents |
[edit] Overview
Public contracting authorities must leave a period of least 10 days between a contract award decision and the formal award of the contract. This is known as the standstill (Alcatel) period. It is a legal requirement for all public contracting authority procurement processes covered by the full scope of the EU Procurement Directives.
The purpose of the standstill is to allow unsuccessful bidders the chance to obtain more information on the award of the contract so they can take appropriate action if they believe they have been unfairly treated.
The term 'Alcatel period' derives from two European cases (C81/98 - Alcatel Austria v Bundeministerium für Wissenschaft und Verkehr and C212/02 - Commission v Austria) which brought about the change in the law.
[edit] What does it apply to?
The period applies to ‘public contracting authorities’ for the supply of goods, works and services contracts above the threshold value. These thresholds range from around £156,000 for essential local government supplies and services contacts (£101,000 for central government) up to around £3,927,000 for works contracts. Similar regulations apply to utilities companies.
[edit] Beginning of the standstill period
The commencement of the standstill (Alcatel) period is from the date the authority decides to award the contract. At this point, the authority will produce an Alcatel letter indicating the beginning of the standstill. This provides bidders with the opportunity to challenge the award decision before the contracts are signed.
[edit] Duration of standstill
The standstill (Alcatel) period will last from 10 to 15 days, depending on the method by which the Alcatel letter is communicated.
It is usual that if the means of communication is electronic, that the time period will be 10 days. However, if the means is to be non-electronic then this can be either 15 days from the date of sending, or 10 days from the date of receipt.
[edit] Legal background
The Public Contracts Regulations 2006 implement into law the European Commission’s Directive on public procurement (2004/18/EC).
[edit] Timeline
The 10-day period is usually scheduled as follows:
- Day 0: Notification of award decision through the Alcatel letters.
- Day 2: Deadline for unsuccessful bidders to request an ‘accelerated debrief’. This can be a means of obtaining information that may facilitate a challenge to the award.
- Day 3 to 7: Responses must be made to debriefing requests during this period. Should there be delays in providing the necessary information the standstill period can be extended.
- Day 10: Standstill period ends at midnight.
- Day 11: If no legal challenge is brought forward, the final award of the contract is made.
In 2009, the provision for an accelerated debrief changed, with the necessary details relating to the contract award decision needing to be provided to all unsuccessful bidders without them having to request it by the end of Day 2.
For more information, see Accelerated debrief.
[edit] Related articles on Designing Buildings Wiki.
- Accelerated debrief.
- Breach of contract.
- Construction contract.
- Contract award.
- Contract conditions.
- Contract documents.
- Contract v tort.
- Contracts under seal v under hand.
- Essentials of a contract.
- Framework contract.
- Government Construction Strategy.
- Letter of award.
- OJEU procurement practices.
- PFI.
- Procurement route.
- Public procurement.
- Social value act.
- Sub-contract.
- Tender documentation.
- Tender processes.
[edit] External references
- Public Contracts Regulations 2006.
- Directive on public procurement (2004/18/EC).
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.