ACM PE panels, ACM FR panels and other variations
ACM PE panels, is short for Aluminium composite material rainscreen panels with a polyethylene core. These are a relatively standard construction product with a long complex history, they also became infamous for their use on the Grenfell tower tragedy. For a detailed look at the developments and changes in their use, see the article ACM cladding.
ACM is a generic term for all types of cladding systems, which are essentially two or more layers of aluminium sandwiching and insulation product, of which there are many variations. Many consider a key element as being the type of insulant or core that is used, which is often (but not always) reflected in the product name. ACM PE; refers to the polyethylene core, ACM PUR; refers to a polyurethane core and ACM FR normally refers to a mineral filled thermoplastic. FR in this case perhaps less descriptive of the actual material make-up stands for Fire Resistance, which is generally achieved by using a mineral filler in the thermoplastic. Other ingredients might also be used in the make-up of the, often, predominantly thermoplastic material such as fire retardants, additives and thermoplastic modifications, all of which can impact both thermal and fire resistance properties.
Mineral or inorganic fillers for the thermoplastics used in ACM cores, fill cells in the thermoplastic helping to improving fire performance, however the percentage of mineral filler can vary from between 5-50%, in comparison with the percentage of thermoplastic, and the data relating to make-up is not always clearly stated.
Whilst the make up of the core can significantly alter the resistance to fire, the panels do primarily rely on the metallic skin to protect the inner core from weathering and from exposure to fire. ACM's are a popular product because of their preciseflatness, variety of surface finishes, colours, textures and so on, they are light weight and flexible. However, incorrect cutting, installation and location of firebreaks between the panels can expose the inner core from the sides or corners, impacting fire resistance, and during a fire, it is possible for the panels to delaminate, exposing the core material.
The University of Queensland, Australia have tested and studied a number of different cladding system and published their results in a library https://claddingmaterialslibrary.com. This library lists some 80 plus products that have been tested, many of which are ACM products, of the those products the library highlights slight variations in the make up of the differing products (even where the descriptive names such as ACM PE or ACM FR remain the same). Some of these are listed below, for further information and detailed results visit the library here:
- ACM with predominantly polyethylene core (ACM PE)
- ACM with predominantly polyethylene and a fire retardant (ACM PE)
- ACM with a mineral (or in organic material) filled thermoplastic core (type of thermoplastic used is often undefined) (ACM FR) FR standing for fire resistant.
- ACM with predominantly polyethylene modified with vinyl acetate (PE-VA)
- ACM with predominantly polyethylene modified with vinyl acetate (PE-VA), a fire retardant, and / or an inorganic filler.
- ACM with predominantly polyethylene (PE) with ethyl vinyl acetate (EVA) copolymer, a fire retardant, and an inorganic filler
Featured articles and news
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Building Engineering Business Survey Q1 2025
Survey shows growth remains flat as skill shortages and volatile pricing persist.