Underreaming
Underreaming is a process used to widen the foot of a bored hole or foundation pier so as to increase its loadbearing area.
It is generally undertaken for safety and/or efficiency reasons, or because of restrictions in the ground, that prevent the use of a pier or pile that is wider along its entire length, and is most common on offshore drilling operations, exploration wells, extended reach drilling, and so on.
Underreaming may also be carried out to create tension piles, where the widened foot resists uplift forces that might otherwise cause the pile to be extracted from the ground. For more information see: Tension pile.
It can also be used in the formation of ground anchors.
Typically, the process involves a drill pipe with cutter blades that can be forced open by pumping a fluid into the pipe. The underreaming tool is kept open by the drilling weight and hydraulics from the pump pressure. The pumps are disengaged when the desired depth has been reached. The underreamer closes and is pulled out of the hole.
It may be necessary to use water flushing systems to remove the reamed spoil from the hole and grout to maintain the integrity of the underream.
There is the risk that if the underreamer is left in the hole for too long, the amount of material left in the hole increases. Also, if penetration rates are too high, this can result in a corkscrewed, under-gauged hole.
It is possible to drill a pilot hole and then underream, or to drill and underream as part of the the same drilling operation.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Shortage of high-quality data threatening the AI boom
And other fundamental issues highlighted by the Open Data Institute.
Data centres top the list of growth opportunities
In robust, yet heterogenous world BACS market.
Increased funding for BSR announced
Within plans for next generation of new towns.
New Towns Taskforce interim policy statement
With initial reactions to the 6 month policy update.
Heritage, industry and slavery
Interpretation must tell the story accurately.
PM announces Building safety and fire move to MHCLG
Following recommendations of the Grenfell Inquiry report.
Conserving the ruins of a great Elizabethan country house.
BSRIA European air conditioning market update 2024
Highs, lows and discrepancy rates in the annual demand.
50 years celebrating the ECA Apprenticeship Awards
As SMEs say the 10 years of the Apprenticeship Levy has failed them.
Nominations sought for CIOB awards
Celebrating construction excellence in Ireland and Northern Ireland.
EPC consultation in context: NCM, SAP, SBEM and HEM
One week to respond to the consultation on reforms to the Energy Performance of Buildings framework.
CIAT Celebrates 60 years of Architectural Technology
Find out more #CIAT60 social media takeover.
The BPF urges Chancellor for additional BSR resources
To remove barriers and bottlenecks which delay projects.
Flexibility over requirements to boost apprentice numbers
English, maths and minimumun duration requirements reduced for a 10,000 gain.
A long term view on European heating markets
BSRIA HVAC 2032 Study.
Humidity resilience strategies for home design
Frequency of extreme humidity events is increasing.
National Apprenticeship Week 2025
Skills for life : 10-16 February