The Pentagon
Contents |
[edit] Introduction
The Pentagon is the headquarters of the United States Department of Defence and one of the largest office buildings in the world. Located in Arlington County, Virginia, it has become a symbol of military power.
The Pentagon was designed by architect George Bergstrom and built by contractor John McShain. It provides around 600,000 sq.m (6.5 million sq.ft) of accommodation, of which 340,000 sq.m (3.7m sq.ft) serve as offices for approximately 23,000 military and civilian employees.
A large defence hub was urgently needed during the Second World War. Initially, President Roosevelt was said to favour a building without windows to protect against possible air raids, although he was persuaded otherwise by engineers, in favour of the five-sided design by Bergstrom.
The building has five storeys above ground, two levels below ground, and five ring corridors per floor, creating a total of 17.5 miles (28.2 km) of corridors. It has a height of 23 m (77 ft), and each of the five sides is 281 m (921 ft) long.
‘Ground Zero’ was the nickname for the central plaza measuring five acres (20,000 sq. m), because it was presumed to be a major target for the Soviet Union during the Cold War.
[edit] Design and construction
Bergstrom was forced to use an asymmetrical five-sided shape for his design because of the position of existing roads on the site. The site itself previously contained housing occupied by the descendants of former slaves. However, it was not large enough for the massive complex being planned, and so a further 150 families were evicted from their homes and their land appropriated.
Because the site is located on the floodplain of the Potomac River, the ground conditions presented a number of engineering challenges. So too did the varying elevations across the site, which ranged from 3-12 m (10-40 ft) above sea level.
One of the first design stipulations was that the building be no taller than five storeys due, in part, to concerns over disrupting the views to and from the Virginia site and nearby Washington D.C. Another reason was because of the steel shortage as a result of the ongoing war effort.
Ground was broken and construction began on September 11 1941. It was built as a reinforced concrete structure, using 680,000 tons of sand dredged from the nearby Potomac River.
As a result of the urgent need for the building, the architectural and structural design work proceeded simultaneously with construction, with construction overtaking design at certain points, the result being that different materials were used from those specified in the plans. A workforce of more than 15,000 worked on the project around the clock, and the first employees moved in to the complex before it was completed.
Construction took place at a time when there was legally-mandated racial segregation. As a result, the building has twice the number of toilet facilities needed, separated by race as well as gender.
The construction of the Pentagon was completed in approximately 16 months, and dedicated on 15 January 1943. The pressure to complete however, meant that costs had spiralled from $35m up to $63m.
[edit] Post-completion
The Pentagon became synonymous with protests during the Cold War, and particularly during the Vietnam War.
The Pentagon underwent a major renovation, beginning in 1998. This involved bringing the building up to modern standards, removing asbestos, improving security, and sealing all office windows. This meant the original system of cross-ventilation from openable windows had to be replaced with air conditioning.
On September 11 2001, on the 60th anniversary of the building's construction beginning, a hijacked airliner was flown into the western side of the Pentagon, killing 189 people. In the aftermath of the attack, the Phoenix Project was launched, a repair and renovation initiative, completed in February 2003 at a cost of some $5bn. In 2008, a memorial garden was opened to the public.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.