Interim certificates in construction contracts
Contents |
[edit] What are interim certificates?
Interim certificates provide a mechanism for the client to make payments to the contractor during the construction process, before the works are complete. The Housing Grants, Construction and Regeneration Act, states that a party to a construction contract in excess of 45 days is entitled to interim or stage payments.
[edit] How are interim payments made?
Interim payments can be agreed in advance and paid at particular milestones, but they are more commonly, regular payments, the value of which is based on the value of work that has been completed (this is the actual value of the work completed, taking into account variations, etc.).
The amount of these payments is entered onto an interim certificate (generally valued by the cost consultant, perhaps having taken advice from the lead designer) and the client must honour the certificate within the period stipulated by the contract.
If the client intends to pay a different amount from that shown on the interim certificate, then they must give notice to the contractor of the amount they intend to pay and the basis for its calculation (pay less notice)
For more information see: Housing Grants, Construction and Regeneration Act.
[edit] How are interim payments valued?
The value of interim certificates is the value of the work completed, less any amounts already paid, less retention. Half of this retention will be released on certification of practical completion and the other half upon issue of the certificate of making good defects.
Interim certificates should make clear the amount of retention and a statement should also be prepared showing retention for nominated sub-contractors if there are any. The contract may require that retention is kept in a separate bank account and that this is certified. In this case, the client will generally keep any interest paid on the account.
For more information see: Retention.
There may be provision to include the value of particularly costly materials that the contractor has not yet delivered to site. This allows the contractor to order items in good time, without incurring unnecessary long-term expense, but does put the client at some risk if the contractor becomes insolvent.
For more information see: Off-site goods and materials.
On design and build projects, the amounts certified as payable may be based on the contract sum analysis.
The contract conditions provide that the contract administrator must issue an interim certificate within five calendar days of the due date whether or not the contractor has issued an interim payment application. This five calendar day period is set by statute in the Housing Grants, Construction Regeneration Act 1996 as amended by the Local Democracy, Economic Development and Construction Act 2009.
For more information see: Payment notice.
[edit] Related articles on Designing Buildings
- Activity schedule.
- Certificate of making good defects.
- Certificates in the construction industry.
- Contract sum analysis.
- Cost value reconciliation.
- Drawdown.
- Due date.
- Final certificate.
- Housing Grants, Construction and Regeneration Act.
- Interim valuation.
- Off site materials.
- Milestone payment.
- Payment notice.
- Payments to nominated sub-contractors.
- Practical completion.
- Retention.
[edit] External references
- RICS Valuations for interim certificates.
- Allan K Construction contracts 2017 @qs 2 kings entertainment
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
Comments
[edit] To make a comment about this article, or to suggest changes, click 'Add a comment' above. Separate your comments from any existing comments by inserting a horizontal line.
Interim Payment Certificate is prepared by Consultant's Team Leader or Contractor's Project Manager's which reports Monthly progress schedule and progress cash-flow.