Indemnity clauses in design and construction contracts
An indemnity clause in a contract allocates risk for claims or for loss or damage between the parties to the contract, so that if one party suffers a loss, the other party will reimburse them. Indemnities are primary obligations that remain even if the contract is set aside.
Indemnity clauses are commonly used on construction projects to allocate risk between; the client and contractor, the client and consultants or the contractor and sub-contractors. In complex contracting situations indemnity clauses may run throughout the contractual chain.
Construction contracts may, for example, include a clause requiring the contractor to indemnify the client against expense, liability, loss or claim in respect of personal injury or death of any person arising out of the works. Or they may require the contractor to indemnify the client against breaches of contract such as non-payment of statutory fees. In addition, designers appointment agreements may include an indemnity in respect of claims for breach of professional duty.
Typically, designers are required to hold professional indemnity insurance to cover such a liability and this requirement is now increasingly asked of contractors with design responsibilities. (See Legal indemnities for a list of other situations where insurance can indemnify against losses).
Performance bonds and parent company guarantees may also include indemnity clauses requiring the surety to indemnify the client against default by the contractor.
The precise consequences of an indemnity clause will depend on its wording and how it is read in relation to the rest of the contract. One particular area where differences can be significant is whether a clause requires an indemnity only against losses caused by the party providing the indemnity, whether they exclude negligence on the part of the indemnitee, or whether they cover all losses no matter how they were caused. For example, a professional indemnity insurance policy is not dependent on allocating blame to the indemnifier.
Because of these differences, and in order to accurately define the extent of losses covered, indemnity clauses require very precise drafting, and due to complex case law they are becoming increasingly detailed. It is important therefore that the parties to a contract read indemnity clauses carefully and fully understand the obligation they are agreeing to.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
New Great British Energy partnership launched
Crown estate help to turbocharge energy independence.
ECA Industry Awards 2024 shortlist revealed
22 leading businesses from across the electrotechnical and engineering services sector.
Government unveils Skills England strategy
Skills England to transform opportunities and drive growth.
New Government Hub for York Given Planning Green Light
For up to 2,600 civil servants, due for completion by 2028.
Construction Skills Certification Scheme cards
July update on Professionally Qualified and Academically Qualified Person Cards.
BSRIA Briefing 2024, November 22
Sustainable Futures: Redefining Retrofit for Net Zero Living.
The CLC on driving competency in the retrofit sector
Previously published roadmap on skills for net zero.
The first labour government King's speech in fifteen years
Construction industry reactions, support and some concern.
CIOB Retrofit of Buildings Technical Information Sheet
What retrofit is, the approach to be taken and processes to be followed.
Adapting Historic Buildings for Energy and Carbon Efficiency
Historic England advice note 18, free download published.
10 retrofit projects revisited 10 years after completion.
Information orders, building liability orders and SPVs
Key BSA terms and how they impact special purpose vehicles.
Listed despite problems with its design.
Zen and the art of cycling exploration.
Design Council Homes Taskforce launched
To support government 1.5 million homes target within UK climate commitments.