Contractual chain
It is common practice on construction projects to have more than one set of parallel contractual arrangements in place. On the one hand there is the main contract between the employer (client) and the main contractor; on the other hand, there is the sub-contract between the main contractor and the sub-contractor or sub-contractors. Each of these contractual arrangements is regarded as a link in the overall contractual chain.
One of the features of the contractual chain is the privity of contract. This means that the rights and obligations contained in the contract apply only to those who are a party to it. So, the main contract between the client and main contractor does not involve the sub-contractor who is therefore not liable contractually to the client for any actual breach of contract. The subcontractor therefore cannot claim against the client for say, poor working conditions or for retention monies held by the main contractor which have yet to be received. The sub-contractor must claim against the main contractor.
Likewise, the sub-contract between the main contractor and the sub-contractor does not involve the client. If the client wishes to claim against the sub-contractor, whether for the latter committing breach of contract or for defective work, the claim must be redressed by the main contractor. In such cases, the sub-contractor is liable to the main contractor.
There is usually no privity of contract between the client and the sub-contractor (whether nominated or domestic). So, for whatever breach of contract, fault or misdemeanour, the sub-contractor is not usually liable to the client. Which means the client cannot claim against the sub-contractor but must recover any due costs from the main contractor (with whom they have privity of contract). The main contractor in turn recovers the costs from the sub-contractor. This amounts to a chain of liability, where recovering costs requires either going up or down the contractual chain.
Problems can arise where the chain involves a weak link. For example, if the terms of the main contract and the sub-contract are not comparable, are incompatible or are just different, relying on the chain of liability could be problematic. There may be a break in the chain which would see the sub-contractor unable to recover any payments or compensation which are rightly due.
On large or complex projects, responsibility and performance generally cascades down the supply chain to a plethora of suppliers, some of whom may be entirely unknown to management at the top of the chain.
For more information see: Supplier and Supply chain.
NB Collateral warranties are agreements which are associated with another 'primary' contract. They provide for a duty of care to be extended by one of the contracting parties to a third party who is not party to the original contract. A typical example would be where an architect of a development owes a duty of care to an occupier of the development in so far as any subsequent defects which may arise are concerned. Privity of contract rules would prevent any liability arising between the architect and occupier without the existence of a collateral warranty.
For more information see: Collateral warranty.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.