Design intent
Contents |
[edit] Introduction
The term 'design intent' is an ambiguous one with several different possible meanings.
[edit] Client intent
ASHRAE Guideline 1-1996, The HVAC Commissioning Process, defines the term 'design intent' as '…a detailed explanation of the ideas, concepts, and criteria that are defined by the owner to be important'.
It suggests that this is developed before the design process begins and sets out what the 'owner' thinks is important. It defines the engineer's scope of work from the owners perspective and may be developed by the owner in conjunction with the engineer. Setting out intent in this way provides a mechanism by which subsequent proposals can be assessed to verify whether they satisfy the intent.
[edit] Early design stages
The term 'design intent' is sometimes used to refer to early design decisions, that is, what the designer intends to design. This has resulted in a whole range of documentation prepared in the early stages of a project being marked as 'design intent', when in fact they just set out preliminary design thinking.
[edit] Designer's intent
Designer's intent may refer more specifically to drawings and other information prepared by the project team that convey the fundamental, intrinsic requirements of a design. Where drawings go beyond showing just these basic requirements and include more detail, they might be referred to as working drawings.
Shop drawings are then prepared by contractors, subcontractors, suppliers, manufacturers or fabricators. These take the design intent drawings and other information and develop them to show in detail how the component will actually be manufactured, fabricated, assembled or installed.
Shop drawings can then be reviewed by the project team to determine whether they meet the design intent.
[edit] Design intent model
PAS 1192-2:2013 Specification for information management for the capital/delivery phase of construction projects using building information modelling (BIM) (now replaced by BS EN ISO 19650) suggests that during the design process, the initial version of the building information model developed by design suppliers might be described as the 'design intent model'.
This should show, '…the architectural and engineering intentions of the design suppliers'. Then, when ownership of the model is transferred to the construction suppliers, it is developed into a virtual construction model containing all the objects to be manufactured, installed or constructed.
See Design intent model for more information.
[edit] Parametric modelling
Building information modelling (BIM) has introduced a certain amount of parametric modelling into mainstream building design.
Parametric modelling (or parametric design) is the creation of a model based on a series of pre-programmed rules or algorithms known as 'parameters'. That is, the model, or elements of it, are generated automatically by internal logic arguments rather than by being manually manipulated.
It is important when using parametric modelling that the 'design intent' is clearly understood and properly defined so that if an element changes, the design intent remains intact. For example, if a junction needs to be in the middle of an element, it needs to be expressed that way, rather than as a fixed dimension from an edge, because if the size of the element changes, the junction needs to remain in the middle, rather than the original distance from the edge.
See Parametric modelling for more information.
[edit] Descriptive information
NB The RIBA Plan of Work published by the RIBA in 2020 defines descriptive Information (or design intent) as: ‘The means by which the design team describes a Building System in a manner that allows a specialist subcontractor to design the system.’ For more information see: Descriptive information
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.
Internally insulating a historical building
An experimental DIY approach using mineral thermal lime plaster.
Tree species selection for green infrastructure: A guide for specifiers.
50 million new trees over 25 years.
Art of Building CIOB photographic competition public vote
The last week to vote for a winner until 10 January 2025.
The future of the Grenfell Tower site
Principles, promises, recommendations and a decision expected in February 2025.
Comments
The use of BIM and VR has now been consolidated into a framework known as Virtual Design and Construction (VDC) that outlines the implementation of a fully digital workflow from design to construction. This is currently being pioneered by certain countries like Singapore that is pushing for a greater shift to digitisation within the industry.
Read More at https://vrcollab.com/posts/why-include-vr-in-bim-execution-plan/