A solution to handle large and complex construction projects: Interface Management
Most large, complex construction projects fail. In fact, “Nine out of ten mega-projects have cost overruns; overruns of up to 50% in real terms are common, more than 50% are not uncommon” (Flyvbjerg, 2014).
In the oil and gas industry, 64% of projects are dealing with cost overruns, and 73% are facing delays in the schedule (Prieto, 2015). Independent Project Analysis, Inc. (IPA) reports 14 of the industry’s largest projects have experienced 46% cost growth over project sanction.
Poor performance of these projects could be related to difficulty in managing multiple scope packages, and lack of effective communication and collaboration across multiple engineering, procurement and construction (EPC) contractors. What this adds up to —along with the emergence of new technologies, the continuing trend toward modularisation and more outsourcing to multiple parties, and geographic and geopolitical influences from regions all over the world — is increasing complexity and thus increasing risk of failure. Other industry sectors face this problem and have begun to address it with interface management.
Interface management has been widely used in the aerospace industry and high-tech manufacturing, where there are lots of modularised components. NASA has developed interface management procedures to identify, control, and verify interfaces to assure compatibility and achieving the highest time and cost performance.
In construction, informal interface management has always been a part of project management practices and project managers' duties; however, it is now emerging as an independent discipline in the oil and gas, offshore, and infrastructure and rapid transit industries. Specifically, significant advancement in information and communication technologies in the past two decades make it easier to adopt interface management processes by medium- and large-scale construction projects.
Major owners and EPCs — such as Suncor, Saudi Aramco and Fluor — have developed formal interface management procedures to minimise the risks of their projects. They have established dedicated teams to implement interface management principles and practices, and in many cases, interface management has become part of organisational best practice.
These companies believe that interface management improves alignment between project stakeholders and reduces project issues and conflicts by increasing the visibility and clarity of roles, responsibilities, and deliverables. It is a logical argument that any project that is highly complex — such as an urban light rail project or an offshore oil platform — could merit the application of interface management.
Despite the evident advantages, interface management adoption in the construction industry is sparse. One of the main reasons could be lack of documented evidence of the benefits of interface management systems.
An interface management research team supported by the Construction Industry Institute (CII, 2014) addressed this question by studying over 45 mega-projects. According to their results, on average, large complex projects using mature interface management systems experienced an average of only 4% cost growth, while similar projects without mature interface management system averaged 18% cost growth. This correlates to almost five-times better cost performance related to formal interface management system implementation.
Based on anecdotal evidence, the cost of interface management implementation (dedicated team, tools and software) for a US$10bn project is approximately 0.2% of total project value. Therefore, for a hypothetical project of US$10bn, the cost of implementing IM might be US$20m, and the benefit could be over US$1bn.
As industry leaders realise the benefits of interface management, I foresee it being increasingly implemented in projects with different sizes. Even more benefits will be realised by integrating interface management with other project management processes such as risk management and change management. Project teams will have a higher level of oversight of the project deliverables and can make better and more informed decisions, all of which help improve project performance to gain a competitive edge.
[edit] About this article
This article was written by Samin Shokri, Ph.D, Construction Management, Interface and risk management. [email protected]. It was first published on The Future of Construction website in July 2017 and can be accessed here.
LinkedIn: https://www.linkedin.com/in/samin-shokri-ph-d-438ab511
[edit] References
- Flyvbjerg, B. 2014. What you should know about megaprojects and why: An overview. Project Management Journal, 45(2), 6–19.
- Prieto, B. (2015). Is it time to rethink project management theory?. PM World Journal. IV(III).
- Vipavetz, K; Shull, T.A.; Infeld, S.; Price, J. (2016) Interface management for a NASA Flight Project Using Model-Based Systems Engineering (MBSE)
--Future of Construction 10:15, 20 Oct 2017 (BST)
[edit] Related articles on Designing Buildings Wiki
- Business case.
- Collaborative practices.
- Code of practice for project management.
- Conflict of interest.
- Consultant team.
- Design management.
- Integrated project team.
- Method statement.
- Programme.
- Project manager.
- Receptor.
- Risk assessment.
- Risk in building design and construction.
- Risk management.
- Stakeholders.
Featured articles and news
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The remarkable story of a Highland architect.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.
Access, history and Ty unnos.
The world’s first publicly funded civic park.
Exploring permitted development rights for change of use
Discussing lesser known classes M, N, P, PA and L.
CIOB Art of Building photo contest 2024 winners
Fresco School by Roman Robroek and Once Upon a Pass by Liam Man.
Comments