Section 38 agreement - adoption of highways
Section 38 of the Highways Act 1980 provides that when planning consent has been granted for a new development, developers may ask the highway authority to ‘adopt’ new roads that have been constructed as part of the development, along with associated infrastructure such as drains, lighting and supporting structures.
Adoption means the highway authority agrees to undertake maintenance of the road from an agreed date at the public expense. The agreement between the highway authority and the developer is called a Section 38 Agreement.
The highway authority will be either the Secretary of State for Transport or the local highway authority.
Before entering into an agreement, the developer must have obtained planning permission, including approval of any reserved matters. The planning permission will generally include an indicative layout of the roads to be adopted.
The Section 38 Agreement may contain:
- Details of the relevant planning permission.
- Drawings indicating the extent of the area to be adopted.
- Provision for land dedication.
- Technical drawings of the works needed to be carried out.
- A programme for the works and for the adoption.
- Provision for inspection and certification of the works.
- Agreement regarding the adoption, or not, of supporting structures.
There will be a fee associated with the agreement, covering the cost of; checking designs, preparing the agreement, inspecting the works, and ongoing maintenance of items not essential for highway purposes (commuted sums). There may also be a requirement for a bond from the developer to cover the highway authority against the possibility that the developer fails to properly complete the works, for example if they become insolvent.
The works must be constructed to a design and standard agreed by the highway authority. The developer will be responsible for carrying out the works at their own expense, and for maintenance costs until adoption.
There will generally be a 12 month maintenance period between the completion of the works and the adoption of the roads. If the development is phased, then adoption will generally take place after the final phase is completed. This is because the roads may continue to be used as a means of access by construction traffic.
The procedure necessary to reach agreement can be time consuming and protracted, and so it is desirable to enter into discussion with the highway authority as early in the project as possible.
Section 38 Agreements are often entered into alongside Section 278 Agreements, which allow developers to carry out works to a public highway. This may be necessary, for example, to provide access to a new site or to improve access to an existing site. See Section 278 Agreement for more information.
NB: Section 37 of the Highways Act 1980 enables developers to offer completed roads to the highway authority for adoption. This is generally considered a less desirable route than a Section 38 Agreement.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Adopted highway.
- Community Infrastructure Levy.
- Highways.
- Highway infrastructure and local authorities.
- Manual of Contract Documents for Highway Works.
- Planning condition.
- Planning obligation (Section 106 Agreement).
- Planning permission.
- Reserved matters.
- Section 50 agreement.
- Section 184 agreement.
- Section 215.
- Section 278 Agreement.
[edit] External references.
Featured articles and news
From studies, to books to a new project, with founder Emma Walshaw.
Types of drawings for building design
Still one of the most popular articles the A-Z of drawings.
Who, or What Does the Building Safety Act Apply To?
From compliance to competence in brief.
The remarkable story of a Highland architect.
Commissioning Responsibilities Framework BG 88/2025
BSRIA guidance on establishing clear roles and responsibilities for commissioning tasks.
An architectural movement to love or hate.
Don’t take British stone for granted
It won’t survive on supplying the heritage sector alone.
The Constructing Excellence Value Toolkit
Driving value-based decision making in construction.
Meet CIOB event in Northern Ireland
Inspiring the next generation of construction talent.
Reasons for using MVHR systems
6 reasons for a whole-house approach to ventilation.
Supplementary Planning Documents, a reminder
As used by the City of London to introduce a Retrofit first policy.
The what, how, why and when of deposit return schemes
Circular economy steps for plastic bottles and cans in England and Northern Ireland draws.
Join forces and share Building Safety knowledge in 2025
Why and how to contribute to the Building Safety Wiki.
Reporting on Payment Practices and Performance Regs
Approved amendment coming into effect 1 March 2025.
A new CIOB TIS on discharging CDM 2015 duties
Practical steps that can be undertaken in the Management of Contractors to discharge the relevant CDM 2015 duties.
Planning for homes by transport hubs
Next steps for infrastructure following the updated NPPF.