A schedule of defects (or defects schedule) is issued by the contract administrator at the end of defects liability period. It identifies defects (aspects of the works that are not in accordance with the contract) that have become apparent during the defects liability period.
The contract administrator and the contractor then agree a reasonable period within which the contractor will rectify the defects identified on the schedule. Once the contract administrator is satisfied that the defects have been rectified, they issue a certificate of making good defects which has the effect of allowing the final certificate to be issued, releasing any remaining retention.
It is important to note that the defects liability period is not a chance to correct problems apparent at practical completion, it is a period during which the contractor may be recalled to rectify defects which appear. If there are defects apparent before practical completion, then these should be rectified before a certificate of practical completion is issued. See the article on practical completion for more information.
NB: Under NEC contracts, at, or just after the defects date the supervisor issues a defects certificate, which either certifies that there are no patent defects, or lists any uncorrected defects. This is analogous to the schedule of defects. See Defects certificate for more information.
[edit] Related articles on Designing Buildings
- Certificate of making good defects.
- Contract administrator.
- De minimis.
- Defects.
- Defects certificate.
- Defects liability period.
- Handover to client.
- Latent defects.
- Liquidated damages.
- Migration strategy.
- Opening up works for inspection and testing.
- Patent defects.
- Practical completion.
- Protecting and storing rebar.
- Punch list.
- Remedial work.
- Retention.
- Schedule.
- Schedule of condition.
- Site inspection.
- Soft landings.
- Substantial completion.
Featured articles and news
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.