Retention of title in construction
Typically on construction projects, goods, materials or plant are not paid for until after they have been delivered to site. Even then, the contractual chain may mean that the client pays the main contractor at agreed intervals, and then the main contractor pays sub-contractors and so on.
This can put the supplier at risk, if the buyer (typically the contractor) defaults or becomes insolvent before payment is received. If the contractor has delivered the items and the client has received them in good faith then ownership may be disputed even if the supplier has not been paid in full.
A ‘retention of title’ clause (‘RoT, ‘Romalpa clause’ or ‘reservation of title clause’) allows a supplier to retain ownership of until specified conditions have been met, for example, until payment has been made. This is permitted under the Sale of Goods Act or the Supply of Goods and Services Act which provide that title passes from the seller to the buyer when the parties intend it to, which can be, for example; upon delivery, upon payment or upon use. This can override the general principle that title passes on delivery and can give an unpaid supplier’s title priority over the client’s.
Such clauses need to be clearly worded, it must be established that they prevail over other documentation (such as purchase orders), and they must be drawn to the attention of the contractor and client by the supplier. If the contractor becomes insolvent, or seems likely to become insolvent, the supplier should act quickly to establish their case, giving notice of retention of title, and making clear that payment has not been made.
However, even when properly prepared, retention of tile clauses can be difficult to enforce, as generally, title passes to the client once items are incorporated into the development anyway, irrespective of whether payment has been made, and it can be difficult to establish whether payment has been made, as the client may make stage payments rather than paying in total for specific items.
Other measures a supplier might take to reduce their risk include:
- Checking the financial status of the contractor to assess the likelihood of insolvency before accepting an order.
- Arranging for items to be marked and stored separately to make clear title remains with the supplier.
- Entering into a direct contract with the client.
- Seeking advance payment.
Advance payment can be secured with an advance payment bond and the client’s title established with a vesting certificate, although vesting certificates can be similarly difficult to enforce.
NB: The term ‘Romalpa clause’ refers to the case of Aluminium Industrie Vaassen BV v Romalpa Aluminium (1976) which established the principle of extended reservation of title.
[edit] Find out more
[edit] Related articles on Designing Buildings Wiki
- Advance payment bond.
- Materials on site.
- Off site goods and materials.
- Off-site goods and materials - legal issues.
- Owner.
- Parent company guarantee.
- Retention.
- Vesting certificate.
[edit] External references
- BIS, Retention of title.
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.