Production information
The Construction Project Information Committee (CPIC) defines production information as '...the information prepared by designers, which is passed to a construction team to enable a project to be constructed'.
(Ref. CPIC The importance of production information - The Construction Project Information Committee provides best practice guidance on the preparation of production information.)
Production information is incorporated into tender documentation and then the contract documents.
The quality of production information is extremely important. Unless it is prepared and co-ordinated properly, there will be disputes and delays on site, and costs will be incurred.
Responsibility for production information depends on the selected system of procurement and the chosen form of contract.
On traditional contracts (and management contracts and construction management contracts), production information may be produced by the consultant team, on behalf of the client. Some elements of production information may be produced by specialist contractors, co-ordinated by the lead designer. Any gaps in this information that require specialist input after the tender process should be clearly defined showing abutment details to adjacent work faces and how such work is integrated into the overall scheme.
On other forms of contract (such as design and build or private finance initiative projects), responsibility for preparing production information and co-ordinating information prepared by specialist contractors may lie with the main contractor.
Production information may include:
- Drawings (location drawings, component drawings and dimensioned diagrams).
- Specifications, design criteria and calculations (specification information can be included on drawings or in a separate specification, but information should not be duplicated as this can become contradictory and may cause confusion).
- Bills of quantities or schedules of work (schedules of work are 'without quantities' instructional specifications often produced by designers on smaller projects for pricing, or for items such as builders work and fixing schedules, such as sanitary fittings, doors, windows, ironmongery, light fittings, louvers, roller shutters, diffusers, grilles and manholes).
There should be a particular emphasis on equipment with long manufacturing times, such as switchgear, chiller units, lifts, escalators or bespoke cladding systems, and on front-end construction such as service diversions, demolition, setting out details, underground drainage, piling and groundworks.
Definitions and rules relating to drawn information for 'with quantities' projects are described the New Rules of Measurement. See New Rules of Measurement for more information.
Increasingly, software is used to prepare elements of production information such as computer aided design (CAD) to prepare drawings, common data environments (CDE), and proprietary systems for the preparation of specifications.
The advent of building information modelling (BIM) can allow the automatic generation of all elements of production information from a single co-ordinated model, resulting in a reduction in errors and so costs.
[edit] Related articles on Designing Buildings
- Bills of quantities.
- Building information modelling.
- Common Arrangement of Work Sections (CAWS).
- Concept drawing.
- Construction drawing.
- Construction Project Information Committee.
- Elevations.
- New Rules of Measurement.
- Post-production information.
- Prescriptive specification.
- Procurement route.
- Production information report.
- Schedules of work.
- Shop drawings.
- Specifications.
- Standard Method of Measurement (SMM7).
- Work section.
- Working drawings.
[edit] External references
Featured articles and news
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.
Passivhaus social homes benefit from heat pump service
Sixteen new homes designed and built to achieve Passivhaus constructed in Dumfries & Galloway.
CABE Publishes Results of 2025 Building Control Survey
Concern over lack of understanding of how roles have changed since the introduction of the BSA 2022.
British Architectural Sculpture 1851-1951
A rich heritage of decorative and figurative sculpture. Book review.
A programme to tackle the lack of diversity.
Independent Building Control review panel
Five members of the newly established, Grenfell Tower Inquiry recommended, panel appointed.
Welsh Recharging Electrical Skills Charter progresses
ECA progressing on the ‘asks’ of the Recharging Electrical Skills Charter at the Senedd in Wales.
A brief history from 1890s to 2020s.
CIOB and CORBON combine forces
To elevate professional standards in Nigeria’s construction industry.
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.