Pre-tender estimate for contracts
The pre-tender estimate (PTE) is the final estimate of the likely cost of the works that are described in completed tender documents prepared to seek tenders (offers) from prospective suppliers. The pre-tender estimate itself is not included in the tender documents.
It provides a final comparison with the budget, and along with the cash flow estimate enables the client to confirm that sufficient funds are available before committing to seeking tenders.
It also gives a basis for assessing and comparing tenders when they are returned.
If the pre-tender estimate exceeds the approved budget, an explanation should be provided for the client to consider and issue instructions.
As with the tender documents, the pre-tender estimate should be broken down into a series of packages (even if there will only be one main contract), this will allow easy appraisal of tenders received, which are likely to prepared by contractors based on prices of packages received from sub-contractors. It ensures that the tenders are easily compared with one another and with the pre-tender estimate, and any anomalies or potential savings identified.
The pre-tender estimate should be prepared following a standard approach to estimating such as that defined by the new rules of measurement (NRM).
NB: A post tender estimate is '…a cost estimate carried out after the evaluation of tenders to corroborate the funds required by the employer to complete the building project.' For more information, see Post tender estimate.
[edit] Related articles on Designing Buildings
- Approximate quantities cost plan.
- Bills of quantities.
- Budget.
- Business plan.
- Cash flow projection.
- Contract sum.
- Contract sum analysis.
- Cost consultant.
- Cost plan.
- Elemental cost plan.
- Estimate.
- Estimator.
- Final account.
- Front-loaded costs.
- Initial cost appraisal.
- New Rules of Measurement.
- Order of cost estimate.
- Post tender estimate.
- Tender pricing document.
Featured articles and news
A threat to the creativity that makes London special.
How can digital twins boost profitability within construction?
A brief description of a smart construction dashboard, collecting as-built data, as a s site changes forming an accurate digital twin.
Unlocking surplus public defence land and more to speed up the delivery of housing.
The Planning and Infrastructure bill oulined
With reactions from IHBC and others on its potential impacts.
Farnborough College Unveils its Half-house for Sustainable Construction Training.
Spring Statement 2025 with reactions from industry
Confirming previously announced funding, and welfare changes amid adjusted growth forecast.
Scottish Government responds to Grenfell report
As fund for unsafe cladding assessments is launched.
CLC and BSR process map for HRB approvals
One of the initial outputs of their weekly BSR meetings.
Architects Academy at an insulation manufacturing facility
Programme of technical engagement for aspiring designers.
Building Safety Levy technical consultation response
Details of the planned levy now due in 2026.
Great British Energy install solar on school and NHS sites
200 schools and 200 NHS sites to get solar systems, as first project of the newly formed government initiative.
600 million for 60,000 more skilled construction workers
Announced by Treasury ahead of the Spring Statement.
The restoration of the novelist’s birthplace in Eastwood.
Life Critical Fire Safety External Wall System LCFS EWS
Breaking down what is meant by this now often used term.
PAC report on the Remediation of Dangerous Cladding
Recommendations on workforce, transparency, support, insurance, funding, fraud and mismanagement.
New towns, expanded settlements and housing delivery
Modular inquiry asks if new towns and expanded settlements are an effective means of delivering housing.
Comments
what is cost reconciliation and why is there one on all submitted tenders is required before placing a contract.