Parkwood Leisure Limited v Laing
Parkwood Leisure Limited v Laing O’Rourke Wales and West Limited [2013] EWHC 2665 (TCC)
About the time the Housing Grants Construction and Regeneration Act 1996 (“the Act”) was passed, I recall asking my training principal whether a collateral warranty constituted a construction contract for the purposes of the Act. “Interesting question” came the response. Here’s an interesting answer................
Contents |
Background
Laing O’Rourke (“Laing”) the defendant Contractor was engaged under a standard JCT design and build contract to carry out and complete the design and construction of a swimming and leisure facility for Orion Land and Leisure (Cardiff) Ltd, (“Orion”), the employer. Orion granted a lease to Parkwood Leisure Ltd (“Parkwood”), the claimant, a facilities management company who operated the pool for them.
The building contract contained a term requiring Laing to provide collateral warranties to a number of third parties, among them, Parkwood. Before the works were completed, Laing executed a collateral warranty in favour of Parkwood.
A number of problems arose after the pool was open with Parkwood alleging construction and commissioning defects, mainly defects with the air handling units.
Some of these problems were settled under a settlement agreement made between Parkwood and Laing, however issues with the air handling units persisted so Parkwood sought to claim against Laing under its collateral warranty.
Parkwood brought (CPR Part 8) proceedings for a determination as to whether:
- The collateral warranty amounted to a construction contract for the purposes of the Housing Grants Construction and Regeneration Act which would then enable it to adjudicate its claim.
- The present claim was compromised in the settlement agreement.
The collateral warranty
The collateral warranty contained the following clause: “The Contractor warrants, acknowledges and undertakes that [emphasis added]:-
- 1. It has carried out and shall carry out and complete the Works in accordance with the Contract;
- 3. In the design of Works.....the Contractor...has exercised and will continue to exercise all reasonable skill and care to be expected of an architect......;
- 7. It has complied and will continue to comply with the terms of regularly and diligently carry out its obligations under the Contract.”
The judge, Mr Justice Akenhead, then looked at the definition of “construction contract” and “construction operations” under sections 104 and 105 of the Act and decided that Parkwood’s collateral warranty was a construction contract as the definitions were widely construed and the Act applies to all contracts related to the carrying out of construction operations. The warranty was subsidiary to the building contract which was itself a construction contract. The judge noted wording in the warranty relating expressly to the carrying out and completing of the works, i.e., a prospective obligation to finish the remaining works.
Not all collateral warranties will be construed as construction contracts for the purposes of the Act; that, of course, depends on the wording of the warranty. The judge indicated that warranties which relate to future performance might be considered construction contracts whereas a pointer against may be that all the works are completed with the Contractor warranting the works after completion.
Parkwood therefore succeeded in obtaining a declaration that its collateral warranty amounted to a construction contract for the purposes of the Act thereby opening the door to adjudication.
The settlement agreement
Whilst certain matters relating to the air handling units were settled between the parties in the settlement agreement there was scope to bring claims which did not exist at the date of the agreement. The lesson to be learned here is the old nugget of clear and careful drafting and avoiding ambiguities that can come back to bite by reopening matters previously considered closed.
Conclusion
The court’s decision is an unexpected one for practitioners who assumed the Act did not apply to warranties.
Collateral warranties will now be subject to greater scrutiny in the light of this case. We may now see a resistance among contractors and consultants to grant warranties and a desire to perhaps restrict the number and scope of warranties so that their application is limited to be retrospective only. That inevitably means further complications for the negotiation and drafting of warranties resulting in protracted and costly negotiations.
The decision also raises speculation as to the application of the Act’s Scheme for Construction Contracts and payment provisions to warranties considered to be construction contracts.
The upshot of this could now see the rise of third party rights as circumventing the issues arising from this case. Could this spell the end of the widespread use of warranties which may finally be falling out of favour?
This article was created by construction lawyer --Najma Dunnett as part of an ongoing series of legal articles. Follow Najma on Twitter to keep up to date with the latest changes in construction law @NDunnett_Cons.
Find out more
Related articles on Designing Buildings Wiki
- Adjudication.
- Collateral warranties.
- Construction contract.
- Defects.
- Definition of collateral warranty.
- Housing Grants Construction and Regeneration Act.
- Reasonable skill and care.
- Scheme for Construction Contracts.
- Third party rights.
External references
Featured articles and news
CIOB launches global mental health survey
To address the silent mental health crisis in construction.
New categories in sustainability, health and safety, and emerging talent.
Key takeaways from the BSRIA Briefing 2024
Not just waiting for Net Zero, but driving it.
The ISO answer to what is a digital twin
Talking about digital twins in a more consistent manner.
Top tips and risks to look out for.
New Code of Practice for fire and escape door hardware
Published by GAI and DHF.
Retrofit of Buildings, a CIOB Technical Publication
Pertinent technical issues, retrofit measures and the roles involved.
New alliance will tackle skills shortage in greater Manchester
The pioneering Electrotechnical Training and Careers Alliance.
Drone data at the edge: three steps to better AI insights
Offering greater accuracy and quicker access to insights.
From fit-out to higher-risk buildings.
Heritage conservation in Calgary
The triple bottom line.
College of West Anglia apprentice wins SkillELECTRIC gold.
Scottish government launch delivery plan
To strengthen planning and tackle the housing emergency.
How people react in ways which tend to restore their comfort.
Comfort is a crucial missing piece of the puzzle.
ECA launches Recharging Electrical Skills Charter in Wales
Best solutions for the industry and electrical skills in Wales.
New homebuilding skills hub launch and industry response
Working with CITB and NHBC to launch fast track training.
Comments
To start a discussion about this article, click 'Add a comment' above and add your thoughts to this discussion page.