Early appointment of O&M providers
Contents |
[edit] Introduction
On a typical construction project, the main contractor has between 30 – 40 subcontractors to procure and manage. Procurement is largely driven by the construction plan which means an O&M provider (Operation and Maintenance) is often appointed late in the project.
This creates a problem as the time it takes to collate and review 30 – 40 O&M submissions should not be underestimated. Condensing this activity into a few weeks or months before practical completion (PC) gives the contractor, supply chain and O&M provider little time to manage the task properly. Ultimately, this can lead to project delays or the risk of incomplete O&Ms at PC.
[edit] Issues with late engagement
- Added cost for O&Ms not previously budgeted for.
- Trades already left site and fully paid.
- No standardisation across O&M submissions.
- Increased pressure on site teams close to PC.
- Risk of missing or incomplete O&M submissions.
- Unhappy end client.
Procuring the O&M package early in the project, makes everybody’s life easier, as the dedicated O&M provider can manage the supply chain in line with the construction plan.
O&M templates can be included in trade contracts to ensure a standardised format is followed. Managing trades as they start on site gives enough time to conduct a thorough review process and makes sure a complete and accurate set of O&Ms is delivered at PC.
The end result is less stress for the main contractor at handover and a happy client with all the information needed to run and maintain their building safely and effectively.
[edit] Benefits of early engagement
- Cost certainty – a realistic budget for O&Ms in the cost plan.
- O&M templates in contract documents.
- Free up valuable site resource.
- Trades managed as and when they start on site.
- Plenty of time to conduct a thorough O&M review.
- Smooth, pain free handover at PC.
- Happy client with a complete and accurate as-built record.
Appoint an O&M provider at the start of the project and gain the full benefits of early engagement – a fully managed process delivering a complete and accurate as-built record at PC.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Licensing construction; looking back to look forward
Voluntary to required contractors (licensing) schemes.
A contractor discusses the Building Safety Act
A brief to the point look at changes that have occurred.
CIOB Construction Manager of the Year award
Shortlist set to go head-to-head for prestigious industry title.
HSE simplified advice for installers of stone worktops
After company fined for repeatedly failing to protect workers.
Co-located with 10th year of UK Construction Week.
How orchards can influence planning and development.
Time for knapping, no time for napping
Decorative split stone square patterns in facades.
A practical guide to the use of flint in design and architecture.
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from construction and 50 percent recorded as fall from height.