CESMM4
CESMM4 is the Civil Engineering Standard Method of Measurement, Fourth Edition. It is published by the Institution of Civil Engineers (ICE).
The first edition of CESMM was published in 1976, following the work of a committee set up by the Council of the Institution of Civil Engineers in 1971 to revise the Standard Method of Measurement of Civil Engineering Quantities. The second edition was published in 1985.
CESMM3 was published in Feb 1991 to; reflect changes in working practices and British Standards, to introduce a new class Z for simple building works incidental to civil engineering works, and to enable its use with ICE Conditions of Contract, 6th edition. However, on 1 August 2011, the ICE Conditions of Contract were withdrawn in favour of the New Engineering Contract (NEC). As a result, the ‘contract neutral’ 4th edition, CESMM4 was published in April 2012.
CESMM4 was prepared under the guidance of ICE's CESMM Review Committee. It retains many of the characteristics of CESMM3, but can be used across a range of contract types, including with NEC, FIDIC (Fédération Internationale des Ingénieurs-Conseils) and ICC (Infrastructure Conditions of Contract). Other changes have been introduced to bring it into line with industry practices and to reflect the emergence new technologies. In addition, references to the British Standards have been removed, making the method more applicable to a global audience (the only exceptions being road construction and concrete mixture).
CESMM4 sets out a procedure for the preparation of a Bill of Quantities for civil engineering works, for contracts based on traditional ‘measure & value’ principles. The Bill of quantities enables tenders to be prepared efficiently and can be used to value work completed once the contract has been let.
The work classification system in CESMM4 includes 26 main classes of work commonly undertaken on civil engineering projects and defines; how work is divided into items, the method for describing items, the units to be adopted and the method of measurement.
The contents of CESMM4 are as follows:
- Preface
- Foreword
- Section 1. Definitions
- Section 2. General principles
- Section 3. Application of the work classification
- Section 4. Coding and numbering of items
- Section 5. Preparation of the bill of quantities
- Section 6. Completion, pricing and use of the Bill of Quantities
- Section 7. Method-related charges
- Section 8. Work classification
- Class A: General items
- Class B: Ground investigation
- Class C: Geotechnical and other specialist processes
- Class D: Demolition and site clearance
- Class E: Earthworks
- Class F: In situ concrete
- Class G: Concrete ancillaries
- Class H: Precast concrete
- Class I: Pipework - pipes
- Class J: Pipework- fittings and valves
- Class K: Pipework - manholes and pipework ancillaries
- Class L: Pipework - supports and protection, ancillaries to laying and excavation
- Class M: Structural metalwork
- Class N: Miscellaneous metalwork
- Class O: Timber
- Class P: Piles
- Class Q: Piling ancillaries
- Class R: Roads and pavings
- Class S: Rail track
- Class T: Tunnels
- Class U: Brickwork, blockwork and masonry
- Class V: Painting
- Class W: Waterproofing
- Class X: Miscellaneous work
- Class Y: Sewer and water main renovation and ancillary works
- Class Z: Simple building works incidental to civil engineering works Find out more
In June 2019, ICE published a revised fourth edition of the Civil Engineering Standard Method of Measurement (CESMM4 Revised) which aligns the method with the most recent developments in the industry:
- Enabling users to estimate the cost of a project as precisely as possible.
- Contract neutral, able to be used with NEC, FIDIC and ICC.
- Able to be used internationally.
In September 2020, ICE published CESMM4 Revised: Complete Book Bundle which includes the revised fourth edition of CESMM — CESMM4 Revised, CESMM4 Revised Handbook, and CESMM4 Revised: Examples.
[edit] Related articles on Designing Buildings Wiki
- Advantages of a bill of quantities.
- CESMM3.
- Civil engineer.
- Quantity surveyor.
- Institution of Civil Engineers.
- New Rules of Measurement.
- SMM7.
[edit] External references
Featured articles and news
Cladding remediation programmes, transparency and target date.
National Audit Office issue report on cladding remediation.
HBPT and BEAMS Jubilees. Book review.
Does the first Labour budget deliver for the built environment?
What does the UK Budget mean for electrical contractors?
Mixed response as business pays, are there silver linings?
A brownfield housing boost for Liverpool
A 56 million investment from Homes England now approved.
Fostering a future-ready workforce through collaboration
Collaborative Futures: Competence, Capability and Capacity, published and available for download.
Considerate Constructors Scheme acquires Building A Safer Future
Acquisition defines a new era for safety in construction.
AT Awards evening 2024; the winners and finalists
Recognising professionals with outstanding achievements.
Reactions to the Autumn Budget announcement
And key elements of the quoted budget to rebuild Britain.
Chancellor of the Exchequer delivers Budget
Repairing, fixing, rebuilding, protecting and strengthening.
Expectation management in building design
Interest, management, occupant satisfaction and the performance gap.
Connecting conservation research and practice with IHBC
State of the art heritage research & practice and guidance.
Innovative Silica Safety Toolkit
Receives funding boost in memory of construction visionary.
Gentle density and the current context of planning changes
How should designers deliver it now as it appears in NPPF.
Sustainable Futures. Redefining Retrofit for Net Zero Living
More speakers confirmed for BSRIA Briefing 2024.
Making the most of urban land: Brownfield Passports
Policy paper in brief with industry responses welcomed.
The boundaries and networks of the Magonsæte.
Comments