Building owner's manual - O and M manual
The building owner's manual, or operation and maintenance manual (O&M manual), contains the information required for the operation, maintenance, decommissioning and demolition of a building.
The building owner's manual is prepared by the contractor or the sub-contractor with additional information from the designers (in particular, the services engineer) and suppliers. It is a requirement that is generally defined in the preliminaries section of the tender documentation where its contents will be described, although there may be additional requirements regarding mechanical and electrical services in the mechanical and electrical specification.
A draft version of the document should be provided for the client as part of the handover procedure prior to certifying practical completion. The final document is not usually available in full form until several months after practical completion, as commissioning information often needs to include summer and winter readings taken in the fully occupied building. The preliminaries may require several copies of the building owner's manual and might require an electronic version.
The building owner's manual might include:
- A description of the main design principles.
- Details of the building's construction (such as finishes, cladding, doors and windows, roof construction, and so on).
- As-built drawings and specifications.
- Instructions for its operation and maintenance (including health and safety information and manufacturers' instructions for efficient and proper operation).
- An asset register of plant and equipment.
- Commissioning and testing results.
- Guarantees, warranties and certificates.
- Particular requirements for demolition, decommissioning and disposal.
Much of this information will already exist in one form or another, so preparing the building owner's manual might simply be a matter of compiling and assembling its components.
Over the life of the buildings, the building owner's manual may be developed to reflect changes that take place to the fabric of the building or its systems, along with details of maintenance that has taken place .
The building owner's manual is different from the health and safety file which only needs to include information important to health and safety and does not need to include information about the construction process, contractual information or information about the normal operation of the completed structure.
The building owner's manual may also include a non-technical 'building user's guide' with information for users about environmental controls, access, security and safety systems, etc.
NB - Building owner's manuals might now be referred to as building manuals. For more information see: Building manual.
[edit] Related articles on Designing Buildings Wiki
- BSRIA updates Handover and O&M manuals.
- Building log book.
- Building manual.
- Building user's guide.
- Decommissioning.
- Deferred maintenance.
- End-user.
- Handover to client.
- Health and safety file.
- Maintenance.
- Operation, maintenance and training (OMT).
- Practical completion.
- Preliminaries.
- Soft Landings for owners.
- Technical guide.
- Tender documentation.
- Users.
- Working with maintenance contractors.
[edit] External references
- BSRIA Handover, O&M Manuals, and Project Feedback. A toolkit for designers and contractors (BG 1/2007).
Featured articles and news
Awe-inspiring medieval great barns.
Registered building inspectors
Building types and conflicts of interest updates explaineed.
Engineering services still struggle with labour shortages
According to latest quarterly services survey of the sector.
Infrastructure that connect the physical and digital domains.
Harnessing robotics and AI in challenging environments
The key to nuclear decommissioning and fusion engineering.
BSRIA announces Lisa Ashworth as new CEO
Tasked with furthering BSRIA’s impressive growth ambitions.
Public buildings get half a million energy efficiency boost
£557 million to switch to cleaner heating and save on energy.
CIOB launches pre-election manifesto
Outlining potential future policies for the next government.
Grenfell Tower Inquiry announcement
Phase 2 hearings come to a close and the final report due in September.
Progress from Parts L, F and O: A whitepaper, one year on.
A replicated study to understand the opinion of practitioners.
ECA announces new president 2024
Electrical engineer and business leader Stuart Smith.
A distinct type of countryside that should be celebrated.
Should Part O be extended to existing buildings?
EAC brands heatwave adaptation a missed opportunity.
Definition of Statutory in workplace and facilities management
Established by IWFM, BESA, CIBSE and BSRIA.
Tackling the transition from traditional heating systems
59% lack the necessary information and confidence to switch.
The general election and the construction industry
As PM, Rishi Sunak announces July 4 date for an election.
Comments