Building notice for building regulations approval
There are two ways of obtaining building regulations approval:
- A full plans application, and
- A building notice application.
Generally on larger, new-build projects, a 'full plans' application will be made, meaning that full details of the proposed building works are submitted for approval before the works are carried out. On small projects, or when changes are made to an existing building, approval may be sought by giving a 'building notice'. In this case, a building inspector will approve the works as they are carried out by a process of inspection.
A building notice application can be made with a simple application form, a site plan (if an extension is involved) and the appropriate fee (calculations may also be required for certain aspects depending on the complexity of the project). This means that work can begin very quickly, and need not necessarily involve design consultants.
However, a building notice application leaves the client at risk that completed works might not be approved, resulting in remedial costs. Clients should be certain that their builder is familiar with all the relevant regulations before deciding to follow this route. It is also worth considering that proceeding without a full set of agreed drawings is more likely to result in disputes.
Building control fees for a building notice may be more expensive than for a full plans application.
Building notices cannot be used:
- For building work to which the Regulatory Reform (Fire Safety) Order 2005 applies (generally commercial or industrial buildings).
- For building work close to, or over the top of rain water or foul drains.
- Where a new building will front onto a private street.
Inspections must be arranged in advance by giving notice to the building control inspector. Notice is likely to be required at:
- Commencement.
- Excavation for a foundation, before covering up.
- Foundations, before covering up.
- Damp proof course, before covering up.
- Concrete or other material laid over the site, before covering up.
- Drains.
- Structural timbers, steelwork or concrete, before covering up.
- Completion.
Other inspections may be deemed necessary by the inspector.
If the local authority is not given notice of work for inspection it may require that the work is opened up for inspection.
If the local authority believes the building work contravenes the building regulations, they may serve an enforcement notice requiring alteration or removal of the work that contravenes the regulations. It is not possible to ask for a determination (appeal) of an enforcement notice as there are no drawings upon which a determination could be made.
A building notice is valid for three years after which it will automatically lapse if the building work has not begun.
It is important to ensure that a completion certificate is sought as evidence that the works comply with the regulations. Under changes to the building regulations made in December 2012, Local Authorities must give completion certificates, they should not need to be requested.
NB: Full plans approvals are also subject to inspection during the course of the works, but as long as the work is carried out in accordance with the approved design, the risk of problems is very much lower than for a building notice application.
[edit] Related articles on Designing Buildings Wiki
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.