Architect's instruction
Construction contracts generally give the contract administrator the power to issue instructions to the contractor. These instructions can be called ‘contract administrator’s instructions’ or ‘architect’s instructions’ (AI). We have used the terms ‘architect’ and ‘architect’s instruction’ below, but they could easily be replaced with ‘contract administrator’ and ‘contract administrator’s instruction’.
Broadly, Instructions may be given:
- To vary the works.
- To postpone the works.
- To remedy workmanship, goods or materials which are not in accordance with the contract.
- To sanction a variation made by the contractor.
- In relation to the expenditure of provisional sums.
- To open up work for inspection.
- To carry out tests.
- To exclude persons from the site.
The contractor must comply with the instructions within certain limitations. The contractor has the right to ‘reasonably object’ to an instruction, and instructions can only be given as empowered by the contract. On receipt of an instruction, the contractor may ask the architect to inform them which conditions empower them to make that instruction. Disagreement about the validity of an instruction may result in a dispute being deemed to have arisen, and the dispute resolution procedures of the contract will then come into force.
If an instruction requires a variation in design to be carried out by the contractor (such as on a design and build project), the instruction may be considered to alter the employer’s requirements.
If an instruction constitutes a variation, then the contractor may be required to give a variation quotation, and the works described in the instruction will not begin until the architect has confirmed their acceptance of the quotation.
If the contractor does not follow an instruction, the architect may be required to issue a 'notice to comply' to the contractor. If they still fail to comply, the architect can instruct others to carry out the work and the contractor will be liable for any additional costs incurred. It is important therefore that such costs are properly recorded, and if possible a range of quotes obtained.
Contracts can be vague about the nature of instructions, other than that they should be given in writing. They should also be dated and signed. There are various instruction pro-forma that can be purchased. It is sensible to send an instruction by recorded delivery, or to confirm its receipt in the minutes of subsequent meetings.
If an instruction is given verbally, either the architect should subsequently confirm the instruction in writing, or the contractor should confirm it in writing, and unless the architect tells the contractor that the instruction is incorrect, then the contractor’s description of the instruction will stand. See Confirmation of verbal instruction (CVI) for more information.
Where an instruction is given to open up work or to carry out tests, costs incurred will be added to the contract sum unless they were provided for in the contract bills, or if the work opened up or tested proves to be defective. If such an instruction is given because other similar work, materials or goods were defective, then no addition will be made to the contract sum as long as the instruction is reasonable.
[edit] Related articles on Designing Buildings
- Adjudication.
- Alternative dispute resolution.
- Arbitration.
- Architect.
- Confirmation of verbal instruction.
- Contract administrator.
- Contract sum.
- Compensation events.
- Defects.
- Defects liability period.
- Extension of time.
- Instruction.
- Mediation.
- Provisional sums.
- Relevant event.
- Variations.
- Work instruction.
Featured articles and news
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.
CIOB photographic competition final images revealed
Art of Building produces stunning images for another year.
HSE prosecutes company for putting workers at risk
Roofing company fined and its director sentenced.
Strategic restructure to transform industry competence
EBSSA becomes part of a new industry competence structure.
Major overhaul of planning committees proposed by government
Planning decisions set to be fast-tracked to tackle the housing crisis.
Industry Competence Steering Group restructure
ICSG transitions to the Industry Competence Committee (ICC) under the Building Safety Regulator (BSR).
Principal Contractor Competency Certification Scheme
CIOB PCCCS competence framework for Principal Contractors.
The CIAT Principal Designer register
Issues explained via a series of FAQs.
Comments
To join the debate click 'Add a comment' above.
Dear All I would like to know if people have strong views on how and when costs should be visible to the contractor on an AI. We are using NBS Contract Administrator which allows these costs to be hidden, or displayed.If the cost of an instruction is not known at the point of instructing, surely it would be meaningless to show an arbitrary number. As such, is it ever appropriate to display costs at the point of instruction?In my experience architectural practices deal with this in differing ways, but I suspect there is an approved way of doing it.Thanks!
The consensus of opinion appears to be that whilst the display of costs attached to an AI is optional, transparency is favourable. If you have pre-negotiated a price put it into the AI but be clear what it covers, such as overheads, prelims and profit. If not negotiated state it as a "budget cost" but also define what it covers.