10(4) Party Wall Surveyor Appointments
In order to understand a 10(4) Surveyor appointment we must first have an understanding of serving a ‘Party Wall Notice’ and a ‘10(4) Party wall Notice’ under the Party Wall etc Act 1996.
There are often scenarios where a homeowner (known as the building owner under the Party Wall etc Act 1996) would like to carry out construction works within their home. If the building owner undertakes construction works to their property that fall within the remit of the Party Wall etc Act 1996, they have a legal duty to serve a Party Wall Notice on the adjoining owner notifying them of these works. For example, excavation works can interfere with soil movement and possibly the foundations beneath. As a result, any such works may cause the adjoining owner to have structural or decorative damage to their property.
The adjoining owners who receive these Notices have 3 options available to them:
- Consenting to the works (with or without a Schedule of Condition Report).
- Dissenting to works and appointing their own Party Wall Surveyor.
- Dissenting to works and agreeing in the appointment of an ‘Agreed Surveyor’. An Agreed Surveyor means that one Surveyor acts on behalf of the Building Owner and the Adjoining Owner mutually and impartially.
Once the Notice is served, the Adjoining Owner will be given a 14-day response period under the Party Wall etc Act 1996 (there will also be an additional 2 days added for postage).
If at this point no response is received, then the Building Owner or the Party Wall Surveyor acting on their behalf can serve a ‘10(4) Party Wall Notice’ under the Party Wall etc Act 1996 which is an additional Notice allowing the adjoining owner a final and further 10 days to respond to the Party Wall Notice. Within the 10(4) Notice it will usually state the date the original Party Wall Notice was served and further describe the works that will be taking place in the Building Owner’s property.
If a 10(4) Party Wall Notice has been served and there still isn’t a response form the Adjoining Owner, the Building Owner or Party Wall Surveyor acting on their behalf can now legally proceed with the appointment of Surveyor under Section 10(4) of the Party Wall etc Act 1996, which allows the Building Owner to appoint a Surveyor on behalf of the non-responsive Adjoining Owner(s).
The appointed 10(4) Party Wall Surveyor will act impartially and help agree the Party Wall Award on behalf of the non-responsive Adjoining Owner. The Surveyor will attempt to make contact with the non-responsive owner. If they do begin communication at this stage, then the procedure would follow a similar route to if the non-responsive Adjoining Owner had chosen to dissent and appoint their own Party Wall Surveyor.
If however, the Adjoining Owner still fails to communicate with the appointed 10(4) Party Wall Surveyor , then the Building Owner’s Surveyor and the appointed 10(4) Party Wall Surveyor will work together to carry out an external Schedule of Condition Report, then agree and serve a Party Wall Award which will govern the works the building owner is proposing to carry out.
[edit] Related articles on Designing Buildings Wiki
- Adjoining buildings definition.
- Fence.
- Line of junction notice.
- Party wall act.
- Party structure notice.
- Party wall surveyor.
- Preventing wall collapse.
- Responsibility for boundary features.
- Right of support.
- Trespass.
- Wall types.
- What approvals are needed before construction begins.
- Who Pays for Party Wall Surveyor's Fees?
Featured articles and news
Amendment to the GB Energy Bill welcomed by ECA
Move prevents nationally-owned energy company from investing in solar panels produced by modern slavery.
Gregor Harvie argues that AI is state-sanctioned theft of IP.
Heat pumps, vehicle chargers and heating appliances must be sold with smart functionality.
Experimental AI housing target help for councils
Experimental AI could help councils meet housing targets by digitising records.
New-style degrees set for reformed ARB accreditation
Following the ARB Tomorrow's Architects competency outcomes for Architects.
BSRIA Occupant Wellbeing survey BOW
Occupant satisfaction and wellbeing tool inc. physical environment, indoor facilities, functionality and accessibility.
Preserving, waterproofing and decorating buildings.
Many resources for visitors aswell as new features for members.
Using technology to empower communities
The Community data platform; capturing the DNA of a place and fostering participation, for better design.
Heat pump and wind turbine sound calculations for PDRs
MCS publish updated sound calculation standards for permitted development installations.
Homes England creates largest housing-led site in the North
Successful, 34 hectare land acquisition with the residential allocation now completed.
Scottish apprenticeship training proposals
General support although better accountability and transparency is sought.
The history of building regulations
A story of belated action in response to crisis.
Moisture, fire safety and emerging trends in living walls
How wet is your wall?
Current policy explained and newly published consultation by the UK and Welsh Governments.
British architecture 1919–39. Book review.
Conservation of listed prefabs in Moseley.
Energy industry calls for urgent reform.
Comments